Secant Piling
In the Open Standard
Arun VasanthMember for 17 years
- Created
- 0
- 4
0
Dear Sir
I am facing a problem with our Secant piling Contractor.
They have completed 8 primary piles since last three days.
When they started boring for the secondary piles their machines are broken down and we came to know that their machine and drill bit are not suitable for this task.
Now it’s almost three days over and the concrete is achieving more strength.
Please guide us for the next step.
Regards
Arun Vasanth