Data Date Issues - Help Required Please

Sarah HayesMember for 14 years 10 months
Created
5
2
0

I am having trouble when I reschedule my programme.

My calendars (both work and resource) are set to 10hr days start 7am - finish 5pm.

When I reschedule my data date to be 26-Nov 00:00 - the activities starting on the 26th show as starting at 7:01 - and not 7:00.  This in turn is pushing all my activities starting on 26th out by one date ie. 2 day duration activity starting 26th 7:00 and finishing 28th 17:00.  But instead it is showing the activity as starting 26th 7:01 and finishing 29th 7:01.

I have checked my settings time and time again and nothing seems to be working.

Need help asap please if anyone is out there reading this.

Thanks : )

5 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Sarah Check your dateline

    Hi Sarah

    Check your dateline time.

    Best regards

    Mike Testro

  2. 0
    Sarah Hayes ·

    Thanks Mike. What do you mean

    Thanks Mike. What do you mean by that though?

    I am rescheduling 26th 00:00.

  3. 0
    Mike Testro ·

    Hi Sarah This seems to be

    Hi Sarah

    This seems to be some sort of system glitch which sometime happen with different calendars on tasks and resources

    Are you using the same calendar for both?

    If not try disabling your resource calendar for this excercise.

    Best regards

    Mike Testro

  4. 0
    Sarah Hayes ·

    Hi Mike, I have created this

    Hi Mike,

    I have created this xer in P6 version 7.0 and I have imported into version 6.0. It's fine in version 7.0 but it goes funny in 6.0.

    I am not sure what you mean by disabling the resources calendar as I am unable to not select a calendar for resources.

    I have made sure the calendars for both the project and the resource reflect the same work hours.

    There must be something in the programme that is saying that the activities cannot start at 7:00am but at 7:01am. It has me stumped though as I have tired every single solution I can think of to fix it. 

    My user preferences & admin preferences are both set to 10hr days.

    I have tried adjusting the actual day of the 26th on both calendars to start work at 6:30 (10.5hr) day and then I reschedule the programme 26th 6:30, which I thought might eleminate the problem given the spare 0.5hr but still the activities due to start on the 26th still show as starting at 7:01.

    No matter what data date I schedule the programme to it always shows activities starting at 7:01 on the data date.

    Very frustrating as my remaining durations don't actually equal the difference between my start & finish dates anymore as they are all out by one day.

    Anywho - thanks for your help Mike.

    Regards,

    Sarah

  5. 0
    Rafael Davila ·

    Sarah,I do not use P6 but

    Sarah,

    I do not use P6 but recall hearing about a 1 minute issue between a start milestone and finish milestone.

    http://www.oracle.com/us/042813.pdf

    Page 8 "

    Has the 1 minute issue between a finish milestone and a start milestone been fixed?

    Yes, this was resolved in P6 v6.2

    If you are using a milestone to define project start and it is of the finish milestone type try changing it to the start milestone type.

    Best regards,

    Rafael

    Photobucket

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?