Mid project baseline issues
In the Open Standard
Adam GarnhamMember for 15 years
- Created
- 8
- 2
0
Hi PP members,
I have just entered a project into P6 which is about half way completed. I need to create the baseline for the projects mid way position. To do this i created a new baseline based on the current project, but when I display the baseline bars some of them line up fine (should be equal to current bar) and some of them are miles off?
Why would it do this as I need the baseline to be equal to the current bars?
Can send a screenshot if it helps.
Thank You
Adam
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?