Explain construction project planning bar chart in relation to project cash flow.

Xue ShineMember for 14 years 10 months
Created
1
2
0

Explain construction project planning bar chart in relation to project cash flow.

 

tq

1 reply

Oldest first
  1. 0
    Kannan CP ·

    1. It depends on how you load

    1. It depends on how you load the cost for each activity in the schedule. Check your BOQ with cost.

    2. Discuss with PM, how to distribute the cost to each activities in the schedule

    3. After assigning the cost, you can develop the cash flow curve.

     

    Regards

    Kannan