filter problem
In the Open Standard
Kashif KhanMember for 14 years 11 months
- Created
- 3
- 3
0
I have a resource loaded program which is of 500 activities.
1. I want to filter WBS for a single resource but i cannot get the milestones in that WBS which are the responsibility of same resource becoz in P6 we cannot assign resources to a milestones, now what to do?
2. If i want to filter the same resource under different WBS then what should i write in the filter?
regards,
kashif