Working In Manhours

Sm PumMember for 14 years 11 months
Created
3
3
0

Hi All,

I need a guidline regarding my project.Our client wants the schedule to be loaded with manhours and do not require the trade wise manhours.my question is that when we use the term manhours in general,Does it means only labor units or  non-labor units will be included also? please reply.its urgent

 

Regards.

3 replies

Oldest first
  1. 0
    Jenny Ingco ·

    Hi SUM PUM, You get to use

    Hi SUM PUM,

    You get to use both, I mean Labor like (Project Manager, Engineers, Mason....etc) and for Non-Labor you can use resource type under any name that will be use in the project like (Loader, Excavetor, Materials...etc).

     

    Please, let me know if you need any more info..

     

    Good Luck..

     

    Hanson

  2. 0
    Sm Pum ·

    hanson CaliforniaThank you

  3. 0
    Rafik Bedri ·

    Hi SUM PUM,p6 update is based

    Hi SUM PUM,

    p6 update is based in manhour, than when you update your resources update labor man hour, you can see that whene you change the actual unit in labor man hour you % progress change.

    Best Regards.

    Rafik