Skip to content

Production rate

Sunil BabuMember for 15 years 11 months
Created
3
3
0

Hi friends,

Just a few things for your discussion.

Few production rates are given below.

1.Backfilling   by machine m3.........0.22

2. backfill by labour (with compaction)  LM.......4

3. bulk excavation 45m haul  m3.........0.09

4.Trench excavation by machine LM....1.67

IS IT BASED ON 8HRS OF WORK..?

any body pls explain.

Regards

Sunil.

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Randall I agree that

    Hi Randall

    I agree that pricing books are a good source of productivity rates but you have to consider a number of factors before using them.

    1.  Similarity of installation - ie in Rebar is it insitu fixing or off site prefab.

    2.  Location - productivity in the UK is not the same as that in other contries.

    The most secure source of labour output is in the Price document / BOQ for the project.

    Best regards

    Mike Testro

  2. 0
    Sunil Babu ·

    Hi Randall, Thx for this

    Hi Randall,

    Thx for this information.

    Regards

    Sunil

  3. 0
    Mike Testro ·

    Hi Sunil I have just read

    Hi Sunil

    I have just read your original thread and your question - Are these outputs based on 8 hrs a day is irrelevant.

    You do not say if the output for backfilling is .22m3 per hour or .22hours per m3 but either way the number of hours per day does not come into the equation.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?