Skip to content

Incorporating approved change into the Performance Measurement Baseline (PMB) using P6v7

Steven WilliamsMember for 21 years 5 months
Created
0
4
0

I have used the 'maintain Baselines' function to update a copy of the project contract baseline in order to demonstrate slippage in the current schedule when introducing an approved change.

this has not resulted in the transfer of the 'coded up & filtered' activities being copied into the PMB from the current schedule as i had expected. therefore i can't show the slippage using this process.

can anyone suggest an alternative method ??

i have now unlinked the copied PMB from the current schedule and restored it in order to try another process.

thanks

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?