SCHEDULE PERFORMANCE FACTOR
In the Open Standard
ZQ
Zq qzMember for 23 years 4 months
- Created
- 12
- 5
0
12 replies
Oldest first- 0BEBernard Ertl ·This issue was discussed recently in the Progress Measurement Units thread. If you do not find what you are looking for in there, perhaps you could be more specific as to what you are trying to measure?
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software - 0FGForum Guest ·Moises,
Im not really sure about your question, but the following might be of help.
Using earned value analysis, just change the cost values to quantity values.
The SPI (schedule performance index) field shows the ratio of work performed to work scheduled (BCWP/BCWS). SPI is often used to estimate the project completion date.
How Calculated
SPI = BCWP / BCWS
An SPI ratio greater than 1 indicates that youre ahead of schedule. Likewise, an SPI ratio less than 1 indicates that youre behind schedule. For example, an SPI of 1.5 means that youve taken only 67% of the planned time to complete a portion of a task in a given time period. An SPI of 0.8 means that youve spent 25% more time on a task than was planned.
CPI (cost performance index) field shows the ratio of budgeted (or baseline) costs of work performed to actual costs of work performed, up to the project status date or todays date. Use quantity instead.
How Calculated CPI is the ratio of BCWP (budgeted cost of work performed) to ACWP (actual cost of work performed):
CPI = BCWP / ACWP
Best Uses This value indicates whether you are over or under budget as of the data date.
- 0BEBernard Ertl ·Moises,
Your last two posts are confusing to me. How can you determine a SPI based upon actual hours before the project starts? Perhaps I am still not understanding what you are trying to do....
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software - 0FGForum Guest ·Sorry to be so contrite! but a baseline plan however good or bad assumes 100% efficiency throughout the life of the programme so whether you look at it weekly, monthly the performance index is constant - but it seems a meaningless question - I must be missing something.
However you can assess the risks associated using various techniques - Three-point-estimating is fairly reliable providing the project is not completely new to the organisation. This should give you the earliest/’mid’/latest dates for the project - I suppose you can then set these up as some sort of PPI. - 0BEBernard Ertl ·There are several ways to generate a curve of % complete targets. We graph the cumulative scheduled manhours from ES to EF. Ie. for day 1, total all scheduled manhours on day 1 and divide by the total manhours for the entire schedule. For Day 2, total all manhours for day 2, divide by the total manhours for the entire schedule and add day 1 percentage.
You can also graph the manhours from LS to LF in addition to the above to display a target range for each day (or whatever your reporting period is).
HTH!
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?