Skip to content

Help, % complete doesn't reflect reality

James MorrisonMember for 14 years 1 month
Created
8
4
0

Hi all, i have Project 2003, I'm not an expert and I generally get by (it isn't that important for my job however from time to time it is necessary).

I have a problem that i have one project which has lots of installations, in the beginning requiring more man hours and getting easier toward the end. Currently we are 50% through the projecttimewise but we have installed more than estimated but the % complete column shows much less being based on duration, however the duration really isn't accurate since it might have 10 days for a certain task but that task takes 15 men. Whereas later tasks have 10 days but they are for 1 man. So you see, it doesn't balance out accurately using this method. How the hell can I do it to more accurately reflect the actual completion as opposed to the duration.

As a clear example; if I were to decrease the duration of a task to say 2 days each instead of 16 days the ‘percentage complete’ column of the project would reduce - however completing tasks in a faster time than the duration estimated obviously does not mean that the project is less complete, but rather the opposite. So you see; this column is not a true reflection of the progress so far. Likewise if I were to increase the time it takes to do a task to 20 days each it would increase the ‘% complete’ column.

I'm going nuts here and can't find anything on the web to help. And please keep the jargon for a numpty like me :) 

8 replies

Oldest first
  1. 0
    Anoon Iimos ·

    I suggest you decompose your

    I suggest you decompose your task (or activities) to as much details as you can;

    the more you got details the more it will become accurate;

    if you got details to the minute, then you can allocate your resources (or man-hours) accurately (or maybe nearly).

  2. 0
    James Morrison ·

    I have very detailed tasks

    I have very detailed tasks and the majority are 100% complete. But I have several tasks lasting many days (for 1 man) which make the duration seem longer in total than the tasks that have been completed. Perhaps there is some settings that need to be altered?

  3. 0
    Anoon Iimos ·

    that's what I'm trying to

    that's what I'm trying to say,

    if you are able to decompose your tasks into a daily duration, then you will get rid of longer duration for a single resource;

    then I guess that you will get what you need.

  4. 0
    Shareef Abdul Azeez ·

    There must be other pecentage

    There must be other pecentage complete types in MS Poject 2003. I have not used MSP as such can not be specific.

    It looks you are using Duration percentage complete (OD-RD)/OD.

    In P6 this situation can be handled by performace, units or physical pecentage complete.

     

    Regards

    Shareef A Azeez

     

  5. 0
    James Morrison ·

    No, that doesn't work, i

    No, that doesn't work, i can't get anymore detailed than I have. I have more than 1000 lines. Unless I break it down into what they do every hour which isn't feasible.

    I'll give you a simplified example of the problem:

    It takes 10 men 10 days to perform the first task.

    It takes 1 man 10 days to perform the second task.

    The first task is 100% complete, the second task is 0%. The completion should be 91%, however MS Project says it is 50% (impossible) - it is just calculating from duration (10 days and 10 days) and not taking into account the hours it takes to do it.

  6. 0
    Anoon Iimos ·

    yes of course there are

    yes of course there are differences in calculating % progress;

    if you want to use duration as your factor, then you have to tailor your plan to be adaptable to duration;

    otherwise, you can either use resource units and/or cost;

    or maybe your own weighting factor;

    the software will never tell you what is the right weight factor to use;

    you need to find it out yourself,

    by the way, I've never seen yet if MSP calculates planned % progress (or based on what factor?).

  7. 0
    Christopher Amores ·

    James,   You have to make a

    James,

     

    You have to make a custom formula for the % complete you wish, in your case manhours. You won't be using anymore the Duration % Complete. Apply this formula in the custom field and add it as a column.

    Hope this helps.

     

    Chris

  8. 0
    Patrick Weaver ·

    The telling question to ask

    The telling question to ask the person responsible for each activity is ‘How long do you need to finish this work?’

    The answer is the information you need for managing forward. For more on this see - Managing for Success - The power of regular updates: http://www.mosaicprojects.com.au/Resources_Papers_002.html

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?