Schedule & Performance % Complete are not Summarized at Summary Level.
In the Open Standard
Sm PumMember for 14 years 11 months
- Created
- 9
- 4
0
Hi All
I am Using Primavera P6 Version 8.2.
I have made a programe that is neither loaded wioth cost nor with resources.I am using Duration % Complete.After assigning the current project as baseline when I have updated the schedule I Found that Schedule % Complete is not rolled up to the summary Level.It is entered in front of each activity but not showing in the TOTAL "Band".Same is the case with PErformance % Complete.
Can any one tell me that what I am missing here
RegaRDS
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?