Schedule & Performance % Complete are not Summarized at Summary Level.

Sm PumMember for 14 years 11 months
Created
9
4
0

Hi All

I am Using Primavera P6 Version 8.2.

I have made a programe that is neither loaded wioth cost nor  with resources.I am using Duration % Complete.After assigning the current project as baseline when I have updated the schedule I Found that Schedule % Complete is not rolled up to the summary Level.It is entered in front of each activity but not showing in the TOTAL "Band".Same is the case with PErformance % Complete.

 

Can any one tell me that what I am missing here

 

RegaRDS

9 replies

Oldest first
  1. 0
    Ian Mackrell ·

    Try: Go to Group and Sort and

    Try:

    Go to Group and Sort and check tick box 'show group totals'

  2. 0
    Sm Pum ·

    Yes I Have tried all

    Yes I Have tried all options.The Issue is that when I assign cost to the activities the I am Getting the Summary Of both Schedule & Performance % Complete.But Without Cost When I am using Just Duration % Complete,it is not Available.

    Anyone else Please advise

  3. 0
    Nicos Pozatos ·

    Schedule & Performance %

     

     

    Schedule & Performance % complete are shown on Summary bars only if your programme is cost loaded. A quick work around is to assign the activity duration as a resource to the activities and give a value to the Price/Unit of the resource you have used.

     

    Regards,

     

     

    Nicos Pozatos.

     

  4. 0
    Sm Pum ·

    This is strange as far as i

    This is strange as far as i remember there was a time when we never loaded resources or cost in our pragram still we have worked with schedule and performance percent complete.  I believe that their must be a way to get these two by using durations only.

    Waiting for other experts

     

    Regards

  5. 0
    Shareef Abdul Azeez ·

    Hi Performance % is used for

    Hi

     

    Performance % is used for Earned Value C alculations, as such cost being a metric is normal,,but the Schedule % complete using cost for calculating %complete (Goup Totals) at summary levels is not the right method. At activity level the Schedule % complete is based on duration.

     

    A work around is to manually create a Planned (Schedule) Progress using update progress and viewing the Duration %complete, which summarizes and provides Group Totals using Durations.  

     

    Regards

    Shareef

  6. 0
    Arun R ·

    Dear All,                  I

    Dear All,

                      I what to know is there any internationally accepted standard for work quantity Vs manhour?

    For example 50cubic meter concreting needs this much manhour, like that? Please help......I want to know how resourses can be assigned in activities.

  7. 0
    Stephan Steenkamp ·

    Can anyone help please?   I

    Can anyone help please?

     

    I have saved the baseline and is using it to calculate Schedule % Complete.

    Im using an updated schedule to calculate performance % Complete.

     

    Now my understanding is that when your baseline date is in progress your schedule % Complete will show progress. Now my baseline date has passed and my schedule % complete doesnt show progress. All my other activities show except a few activities. I have tried resource & cost loaded schedules, I have tried changing the settings when calculating but it doesnt work.

     

    Please any help will be appreciated.

  8. 0
    Raymund de Laza ·

    Stephan, Just assign the

    Stephan,

    Just assign the Baseline in the Primary Baseline. Do not assign on the Project Baseline.

    Regards,

  9. 0
    Stephan Steenkamp ·

    Raymund,   Thanks, got it

    Raymund,

     

    Thanks, got it sorted yesterday.

     

    I made a rookie mistake, didnt update my baseline. After the update all was good.