Extract Late budgeted labuor unit and Early budgeted labuor unit

Jay BaskaranMember for 14 years 4 months
Created
2
2
0

Anyone help me how to Extract Late budgeted labuor unit  and Early  budgeted labuor unit  from  

P6.

2 replies

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi JayI suggest to go to the

    Hi Jay

    I suggest to go to the Assignments at the left hand of your screen and use filters and group &  sort to make the selection you desire.

    Regards

    Johannes

  2. 0
    Khaja Sharief ·

    You can get this information

    You can get this information in three windows; (1) activity usage spreadsheet (2) Resource Usage Spreadsheet (3) Resource assignments.

    In all the windows you can right click on the spreadsheet->Spreadfields->Customize->select the field either early or late. 