Total Float -1 with Mandatory Finish

Sarah MoultonMember for 13 years 8 months
Created
1
3
0

I am currently using P6 v7.0. We have just created a project, for the finish milestone, we gave it a mandatory finish of August 23, 2013. All the predeccessor activities complete by August 21, 2013. Yet I am showing a total float of -1. Can someone please help me out??

Thanks!!

1 reply

Oldest first
  1. 0
    Rafael Davila ·

    http://www.slideshare.net/InS

    http://www.slideshare.net/InSyncConference/p6-version-7-tricks-and-traps

    After looking the above reference I suggest avoiding mandatory constraints, they work differently to finish no latter than constraint and are to be used for some analysis but not for actual management and scheduling.