Gentlemen,

Good day.

First of all,I would like to introduce to you myself briefly.My name is Leon Rosario currently working in Hydro-Projects.My previous exposure was purely electro-mechanical(external works).Moreso,in parralel to my working experience in view of scheduling for my new job(civil works).I am facing a problem in reinforcing bars production rate for structures.

I need your help maybe you can give me some links or further information regarding rebars installation productivity rates.

Thank you in advance.

 

Best wishes,

Leon Rosario

  

3 replies

Oldest first
  1. 0
    Bogdan Leonte ·

    After a quick search I found

    After a quick search I found the following:
     

    Rebar Crew Productivity

     
    Slabs 350 lb/ch pounds of steel per crew hour.
    Footings 130 lbs/ch
    Foundation 187 lbs/ch


    Forming Crew Productivity

    Slabs 36 sfca /ch
    Footings 11.5 sfca/ch
    Mat Footing 6.9 sfca/ch
    Foundation 11.84 sfca/ch
    Suspended Slab Underside 10.64 sf/ch
    Suspended Slab Edge/Bulkhead 34.48 lf/ch


    Hope these help.


    Regards,
    Bogdan
  2. 0
    Leon Rosario ·

    Dear Mr.Bogdan,I would like

    Dear Mr.Bogdan,

    I would like to take a quick moment to thank you for such great info.

    Best Wishes,

    Leon Rosario

  3. 0
    Praphuljith Kc ·

    Hello Everyone ,Can any body

    Hello Everyone ,

    Can any body tell me why some activities are show as critical when there is a positive total float for that activity. I believe critical activities have total float less than or equal to zero.

     

    Thank You.