Calender and Hours per time period
In the Open Standard
Rana JiMember for 16 years 10 months
- Created
- 0
- 2
0
Dears
I am facing a problem in Hours per time period settings.
I have to always set these settings,
I have 5 different projects, all project used different calenders.
When i scheduled the program - it shows different dates from the contractor schedule.
What is the problem,
When i export the schedule i-e XER - settings should be set automactically or should i ask what Hours per time period you have set. then i do it accordingly each time.
Please advise
Rana