% complete rol up

Andrew FrancisMember for 13 years 1 month
Created
3
3
0

Hi hope someone can advise -

 

I am new to P6 ( from MS project  environment) and cannot get a %compete figure to roll up into the wbs top level in the activity view (as you can in project).

I have tried it in the WBS layout but is not he same pictorially.

 

we are using straight level of effort no resource assigned and being advised of slips or increasing % ct manually.

 

can someone advise- if i dont respond i am not being rude but dont know how to answer you

 

Andy 

3 replies

Oldest first
  1. 0
    Kaif Mohsin ·

    Dear Andrew,In order to get

    Dear Andrew,

    In order to get 'Percent Complete' figures to be rolled up at different WBS Levels, you need to have cost assigned to the activities because it is calculated from Earned Value, Planned Value and Budget at Completion. So, unless and until you have cost assigned to the activities you will no get any roll up figures at the WBS Level.

    Best Regards,

    Kaif Mohsin

  2. 0
    Andrew Francis ·

    ok thanks very much

    ok thanks very much

  3. 0
    James Shimmon ·

    Also, you would need to use

    Also, you would need to use the 'Performance % complete' field rather than the Physical % - Physical % complete won't rollup through WBS legs

    Cheers

    Shimmo

Log in or join to reply