% complete rol up
In the Open Standard
Andrew FrancisMember for 13 years 1 month
- Created
- 3
- 3
0
Hi hope someone can advise -
I am new to P6 ( from MS project environment) and cannot get a %compete figure to roll up into the wbs top level in the activity view (as you can in project).
I have tried it in the WBS layout but is not he same pictorially.
we are using straight level of effort no resource assigned and being advised of slips or increasing % ct manually.
can someone advise- if i dont respond i am not being rude but dont know how to answer you
Andy
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?