Edit Columns in P6

Patrick OsakweMember for 14 years
Created
2
2
0

Hi All,

Can someone please help me?

I am trying to create a column titled Finish Variance CL14 and Finish Variance Last Period. I have successfully created these but don't know how to edit it or enter the formula to show me the variance/difference in the columns field.

Currently the fields are empty when I add the columns.

Please help!

Regards,

Patrick

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Patrick, If your CL14

    Patrick,

     

    If your CL14 programme is saved as the Project Baseline, and your last period programme is saved as the Primary Baseline, then just insert the existing columns "Variance - BL Project Finish Date" and "Variance - BL1 Finish Date" (found in the durations group)

     

    Then you can edit the column titles to mention CL14 and last period

     

    No need to mess about with custom fields and formulaes.

     

    Cheers,

     

    G

  2. 0
    Patrick Osakwe ·

    Gary, You are the best and a

    Gary, You are the best and a genius. Thank you very much. Regards, Patrick