Man Hours

Ammar TauqeerMember for 13 years
Created
1
4
0

I've completely tracked my project now i want to know my actual manhours how can i know that?

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi AmnarWhat method did you

    Hi Amnar

    What method did you use to allocate resources to your task bars?

    If your modelling is based on duration = man hours / gang size then it is easy to create a graph of both planned v achieved man hours.

    Best regards

    Mike Testro