Skip to content

Procurement Problem

Moutaz AldeibMember for 22 years 9 months
Created
5
1
0

Dear Planners,

I am establishing an EPC Schedule for a water supply project contains 81 Km pipeline and three tanks. For the tanks there are a lot of mechnical items to be procured, what is the best way to include those items in the schedule? I am thinking to include it as one activity rather than include it item by item?

Regards,

Moutaz

5 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Will they be procured as one

    Will they be procured as one item? Will they be designed as one item? Will the be installed as one item? Will they be commissioned as one item?

    No.

    So why would you want to plan them as one item?

     

  2. 0
    Sunil Babu ·

    Why putting as one item ?

     

    Why putting as one item ? Procurement start date and end date is sufficient isn't?

  3. 0
    Rafael Davila ·

    When the delivery of the

    When the delivery of the items is more than one unit to be consumed on different areas the correct way to model the effect of non timely deliveries is by using consumable/nonrenewable resources.

    Activity logic is not enough, even if you create a separate activity for every item it will not do it; say 200,000 bricks delivery activities will not do it, as soon as you have a single brick on site the installation can start but at some point might be interrupted.  

    You cannot model the effect using regular/renewable resources.

    For this reason for many decades such functionality for consumable resources have been available. When you have hundreds of such resources, hundreds of partial deliveries and hundreds of activities competing to use these resources it can become quite complicated to manage the schedule using manual adjustments.

    I started using this functionality over two decades ago with Microplanner V6 but suspect have been around a few additional decades before, it is nothing new. Learn to use this functionality if delivery of materials matter. 

  4. 0
    Johannes Vandenberg ·

    Hi MoutazAs Rafael noted,"if

    Hi Moutaz

    As Rafael noted,"if delivery of materials  matters" then it is essential that every procurement item is individually planned and the ROS ( Required On Site ) is establised. For bulk materials you could  detail the requrements per fase or section.

    Regards Johannes

  5. 0
    Mike Testro ·

    Hi MoutazThere are four

    Hi Moutaz

    There are four stages for material procurement following design.

    1. Approval of the material by the Engineer.

    2. Place order and set up delivery sequences.

    3. Manufacture & delivery - allow for any Factory Inspection Tests (FAT) by the Engineer - there should be as many sections as there are workfronts on your programme.

    4. Take delivery to laydown areas and deliver to any particular workfront.

    These stages should all be set ALAP.

    Stage 1 & 2 can be a single bar linked FS but they must then be linked to work sections in stage 3. 

    I doubt if your 81km of pipeline is all in one single bar - it should at least be in sections between the three tanks so link stages 3 & 4 FS to each work section starting with "stringing out".

    You will then have a responsive procurement programme linked to progress on site - it will also show the immediate affect of any client delays.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?