Urban Planning

Ramin AbasyMember for 14 years 6 months
Created
3
2
0

Dear All,

I am preparing a schedule for urban design, need you cooperation to advise the project phases that we are using for urban planning

 

Thanks

Ramin

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi RaminThis will do for both

    Hi Ramin

    This will do for both design and construction on a green field site.

    Survey

    Site clearance > take out old services - divert live > clear contamination

    Earthworks  > cut fill to profiles

    Infrastrure > roads > drains > services > sub stations

    Structures in phases

    Landscaping > planting > water features

    Best regards

    Mike Testro

  2. 0
    Ramin Abasy ·

    Thanks, But it needs also

    Thanks, 

    But it needs also environmental, land clearance, structure plan, development plan and etc, how do we make for these items a project phase.

     

    Regards

    Ramin

  3. 0
    Mike Testro ·

    Hi RaminYou obviously know

    Hi Ramin

    You obviously know more about the subject than I do so just put things in your programme in the order that they have to be carried out and link them logically - Finish > Start.

    Best regards

    Mike Testro

Log in or join to reply