Setting up Baseline Schedule
In the Open Standard
Albert BalogoMember for 18 years 4 months
- Created
- 3
- 5
0
Hi Planners,
Would you please help me. I was trying to stablish a baseline schedule with the current update (current is not updated yet), but baseline finish daes goes beyond the current dates. The question is HOW TO RESET THE BASELINE SCHEDULE? so that the current and baseline finish dates will be the same.
Thanks in advance
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?