Construction Schedule for Basic Oxygen Furnace/Steel Melting Shop
In the Open Standard
Arun KumarMember for 14 years 6 months
- Created
- 0
- 2
0
Dear Planners,
An anyone please help me out the Overall construction schedule for Basic Oxygen Furnace / Steel Melting Shop for 3.0 MTPA Iron & Steel Plant. The schedule should include excavations & foundations, Structural fabrication & erection, Mechanical Equipments erection, Electrical & commissioning.
Scheule with sequencing for Converter Erection & High Bay Erection would be highly helpful to me.
It will be appreciate if you share it.
Thank you so much.
My ID : arunbssr@gmail.com
Thanks & Regards
Arun Kumar
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?