Import update from PMS(excel) to multiple programs in P6
In the Open Standard
Ayman MohammedMember for 13 years
- Created
- 1
- 2
0
Hi All,
I am a fresh planner and very recently my boss allowed me to start updating the program. The issue is that i am having a baseline and recovery programs and i have to update same activities twice which consumes a lot of time, bcoz first i update the PMS and then take same percentages (for baseline and recovery) in program manually reducing the remaining duration appropriately.
How can i save time by exporting and importing to apply update. i have seen my boss doing it but i dont know how to do it. i know how to use vlookup.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?