Delay by total float vs. delay by variance

Dura CellMember for 15 years 10 months
Created
1
4
0

Hi All!

We are using P6 in our project, one of our consultant is calculating activity delays using the variance dates (BL FInish - Finish), my point of view as a planner is the actual delays in the activity can be viewed once we run the schedule as P6 determines delay after calculating the schedule (critical path).

I would like to ask what is the effective way of computing delays in the activity?
Is it by total float or is it by variance? Any advantages or disadvantages of these two?

Many Thanks!

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    one this assumes that the

    one this assumes that the correct baseline has been assigned ot the current schedule

    the variance dates (BL FInish - Finish) is comparing the finsh dates of the two schedules and will show positive abd well as negative variances between the 2 dates. It is the difference between the activity's baseline and current finish date.

    the variance dates (BL FInish - Finish) will give you values even if the activity has been completed

    when only looking at float values there wil not be any float values once and activity has been completed.

    be careful because there is a difference between the BL Finish the , Finish and the Late Finish Dates

    The BL Finish is the Early Finish date in the baselie schedule

    The Fnish date is the Early Finish date in the current schedule unless its an actual date

    The late finish dates minus the early finish n the current schedule will be used to determine the float values 