Planning and Scheduling with Building Access Date Constraints
In the Open Standard
Fadil RexhepiMember for 14 years 10 months
- Created
- 1
- 3
0
Hi,
I am trying to figure out what will be the best way to show plan when I have constraints on accessing the building to perform installation of items.
For example, I need to access the dates between 1 Dec and 31 Dec, but my parts won't arrive until 15 January. How could I show the 15 January in a Critical Path, that it is affected by the building access dates.
I can post a sample of the activities if someone is willing to help me further.
Regards,