Budgeted Non Labor Units increasing to 8 times when imported to other computer

Shreeraj KhilareMember for 9 years 5 months
Created
1
2
0

Hi, 

Greetings for the day folks.

I am new to a job and i dont know how earlier guy has loaded Non labor units. 

When I am exporting a project and importing to other computer resources are increasing by 8 times.

Please guide me to straighten this thing.

 

Thanks in advance.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    this can happen if you import

    this can happen if you import a p3 project or a ms project into p6.

    did you use any of these ? You have to chage a setting when importing these types of projects

    to fix this go to tools global change

    add 

    up top make under select subject area the sure that is says Activity Resource Assignments

    Where resource equals non labor

    then Budgeted Non Labor Units = Budgeted Non Labor Units / 8

    to get the 8 in the paramater value select {Custom} then this will giev you teh ability to put a value in there

    then on the right select change the bottom select committ changes

Log in or join to reply