Distinguished Planners, PM,

Please i have issues measuring the progress with Ordered and delivered material. I built in every material in my program but the performance % complete keps reading zero wheni filter for procurement. How can i deal with this.

 

Regards

Iyke.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    do you have a resouce

    do you have a resouce assigned to the procurement activites?  if not then u cant get performance