Baseline Schedule Narrative

Muhammad Zahid MahmoodMember for 9 years 1 month
Created
1
4
0

Dear All,

I need a compreshensive narrative report for the baseline schedule, which inlude detailed understanding for anyone involved in the project.

 

Can anyone please share any sample format/templates for the report.

 

Thanks

Muhammad Zahid

zahidmallick126@yahoo.com

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    why not create you own don't

    why not create you own don't ask for others

    Baseline CPM Narrative

    The  Baseline CPM Network narrative should include the folowing:

     

    Ø  Assumptions used in development of the CPM network.

     

    Ø  Actions required by others (owner provided permits, owner provided utilities, owner provided access, owner provided equipment, etc..).

     

    Ø  The critical and near critical paths.

     

    Ø  Description of calendars and how holidays are incorporated.

     

    Ø  How the CPM network has accounted for inclement weather.                    

     

    Ø  How weather may impact certain activities.

     

    Ø  Planned sequencing and phasing.

     

    Ø  Anticipated manpower

     

    Ø  Over all plan for the project.

     

     