Interactive Planning Session Question

Ryan JarreauMember for 8 years 9 months
Created
4
25
0

A few times a month, I facilitate interactive planning sessions between owners and subcontracted engineers and constructors. Normally ill print out a big paper timeline, hadwrite activity descriptions on post it notes and positon them on the timeline before the meeting starts. During the course of the discussion, we'll move the post it notes around to create our baseline plan. After the meeting, I'll input the information into P6 with logic, durations, and resources. At that point our baseline schedeule is created.

 

To me it seems a little unprofessional to handwrite on post it notes, but that's the standard at the company I'm working for. Is there a better way to do this? Does anyone have any tips on how to make an interactive planning session more efficent?

 

Thanks in advance!

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi RyanYou are describing the

    Hi Ryan

    You are describing the "Lean Planning" process which has its use except that you have to do it all over again the next week because nobody actually pays any attention to what the planner says.

    BTW you forgot to mention the pins and string.

    Best regards

    Mike Testro

  2. 0
    Santosh Bhat ·

    Use a more collaborative

    Use a more collaborative Planning and scheduling tool like Netpoint by PMA Technologies.

  3. 0
    Zoltan Palffy ·

    touch plan andand esti

  4. 0
    Ade Afe ·

    Apologies, wrong post

    Apologies, wrong post