DACE labor productivity norms

Michele CiuffredaMember for 15 years 8 months
Created
2
2
0

Hi everybody,

I am leading the planning office of my company mainly involved as EPC contractor in industrial plants and infrastructures.

After many years, I have the opportunity to purchase a database of labor productivity norms. I am trying to find a usable database (USGC or DACE for instance) or like a big excel table I mean in the market. But to now I have not found anything.

The purpose is to use a recognised system to estimate the size of a project from BoQs, and to have a shared system with other offices (proposal, engineering dpt, ...)

Thus, my questions are:

1. can somebody tell me a web site to find DACE labout productivity norms? I have searched a lot but with no success.

2. can somebody tell me if there is some interesting database to have a look? In case please indicate to me the web reference.

Thanks guys

Regards

Michele

PS Pease apologise me if it is the wrong section

2 replies

Oldest first
  1. 0
    Michele Ciuffreda ·

    Hi, is there nobody could

    Hi, is there nobody could provide me a feedback?

    I am also interested even in other types of labour productivity norms/databases you would suggest.

    Thanks

  2. 0
    Steven Auld ·

    Michele, Have you tried the

    Michele,

    Have you tried the Dace website?

    www.dace.nl

    Most of the large EPC companies have their own systems, however another alternative version is available from estimations.info