Schedule vs Engineering process
- Created
- 5
- 2
Hi all, I need your thought regarding a situation in a project.
Does a project schedule that has been accepted by a client which shows a contractor having finished a design goes ahead and places an order for the designed asset, overrides the normal engineering process (not written in contract though) which requires client to review and approve the design? Basically, a contractor is claiming to be right because their schedule shows the relationship i.e. after design, procurement starts, and it means the client accepts that since client did not dispute the schedule. But the client did not focus on the activity relationships and insists it is not liable for breach of process. So, whose side are you on?
5 replies