Why? Or should we/they change logic that completed out of order?

John ReevesMember for 13 years 5 months
Created
1
2
0

When a successor is complete 100% the program just skps to the next successor in the chain, so why should the logic be changed to the way it really happened?  Or should we just leave it to keep from complicating the schedule and comparisons?  I used to be able show how it created a false gap in time in chains when leaving in old logic with "retained" logic but I am not seeing that now.  I know it can "sometimes", do you recall when it does - i assume those should be fixed.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    yes out of sequence logic and

    yes out of sequence logic and be viewed in the P6 log report.

    you can have logic pushing through an activity ie.

    Activity A B and C all sequential 

    Activity A is in progress 

    Activity B is completed 

    Activity C has not started

    Since activity A is not complete the earliest that activity C can begin is when activtiy A is done. Even though activity A is not tied to activity C it is still honoring the retained logic and passes thru activity B to activity C

Log in or join to reply