Rate Change in P6
In the Open Standard
Samuel RotimiMember for 8 years 9 months
- Created
- 5
- 43
0
There was a rate change on my schedule. All ended activities accepted the changes without any issue same with all future activities without actual. My problem is that all Activities that are in progress and exceeded the current data date are still retaining old rate. E.g let say I have an activities that was planned for 6months at £200 the activity started and actual taking in April we made rate change to 250.i expect the 250 to be the new rate for the remaining duration but that is not the case the remaining months keep going back to the original rate. Pls how do I fix this to keep the rate change on the remaining duration
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?


