What is a good labor cost factor % to go to 10hrs/from 8 and 6 dy wk instead of 5 dy wk. = Premium time
In the Open Standard
John ReevesMember for 13 years 5 months
- Created
- 2
- 3
0
In theory, it shouldn't be that much more because you complete the same work faster. If you are going from 40 to 50 during the week, possibly the same resource couldn't work the Sat. But lets assume it does. Does this mean x 1.5 factor x 1/3 of the hours - because 40 of the 60 would be straight time leaving 1/3 of the hours x 1.5. What do you think? I understand we could and should look up the rates per trade etc, this is just to be an estimate against budgeted cost to accelerate.