Manhours Factor
In the Open Standard
Jithin KambhikanamMember for 15 years 6 months
- Created
- 5
- 2
0
Hello Everyone,
Just to clarify a point. For a construction project on what logic is the manhours calculated. For example the manhours for ,
| Dicipline | Unit | Quantity | Manhours |
| Piping | Dia Inch | 1 | 9.67 |
- This includes the workforce starting from the foreman to do the work to the helper (Direct Manpower). This gives the weightage of the perticular dicipline ie as per the quantity of manhours used per dicipline.
- It does not include the hours of equipment used (Crane to lift the pipe and hold) - but include the hours of the operators who runs the equipment.
Could you say if the logic is correct ie,
- Manhours = Hours of Personals used to do the Work
- Manhours = Hours of Personals used to the Work + Equipment Hours used to do the Work.
Warm Regards
Jithin
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?