Weightage Split
In the Open Standard
Jithin KambhikanamMember for 15 years 6 months
- Created
- 2
- 3
0
Hi All,
Need a your view.
I have a made a excel progress measuring sheet in weightage is split by acivity like below table,
| Baseline Activity | Baseline Weightage |
| A | 5% |
| B | 25% |
| C | 35% |
| D | 20% |
| E | 15% |
| Total | 100% |
But now I need to add one more acvitiy as it was missed when developing basline weightage. Please note that the acivity is new and is not related to any of the basline acvitiy mentioned above.
| Actual Activity | Weightage |
| A | |
| B | |
| C | |
| D | |
| E | |
| F | ? |
| Total |
Please advice how to put weigtage as now I need to measure the progress with the new activity.
Thanks
Jithin
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?