Calendar days vs Default calendar days
- Created
- 2
- 3
I searched for threads on similar topics but could not get a definite answer from any of them. The threads were posted several years back. Now hoping that P6 has come up with some genius ways to resolve the same issue.
The issue is, my schedule is calculating the finish dates variance by dividing the variance hours by 12 hours/day instead of the calendar hours of 7hours/day. Hence when you compare the finish dates, it doesn't quite add up. Example shown below.
Fingers crossed: is there any way to command P6 to calculate using the calendar in use rather than the default calendar?
Amongst the geniuses in this group, someone please suggest the easiest solution.