Productivity Calculation for Steel Works

Suhaila TsuMember for 15 years 4 months
Created
1
4
0

Hi all.

I need help on the productivity calculation for structural steel works

How many manpower we should consider for how many tonnage.

Now i have 700ton steel beams and column. It is for the construction of 6 floor factory expansion. The duration is 6month

I need to calculate on the manpower.

Please give me some guidance

Thank u so much in advance

 

 

1 reply

Oldest first
  1. 0
    Joselito Santillan ·

    2.00Steel FixerReinforcement

    2.00Steel FixerReinforcement Steel4.008.001.00ton0.13 Ton/Manday

Log in or join to reply