DCMA 14 and Level 2 schedule
In the Open Standard
Brian WalkinMember for 8 years 9 months
- Created
- 2
- 4
0
Needing a reference or guidance. A L2 schedule should be a roll up from a L3 schedule. Sometimes however a L2 schedule may be an early deliverable long before a L3 is developed fully due to lack of design and/or subcontractor information. Maybe L2 is an incorrect term in this case.
We made the deliverable of the L2 schedule and the client ran DCMA14 on this schedule and of course it does not pass those criteria.
I'm looking for some reference where DCMS applies only to a certain level of schedule. Any input appreciated.