What's wrong with a hard constraint if used properly?

Garson HillMember for 1 month
Created
2
237
0

Hello,

Why should I not use hard constraints in my construction schedule - can't I justify to the client that it is allowed to the contract end date. I thought it would give me a critical path and show it negative float if we start to slip (which we have)?

I thought that was permissible in some cases.

Thanks G.

2 replies

Oldest first
  1. 0
    Muhammad Saaid ·
    Accepted answer#1

    Nothing is wrong with a hard constraint if it reflects a genuine contractual milestone. The problem arises when it overrides schedule logic, hides negative float or masks the true critical path. Use it when justified not as a shortcut to force dates

  2. 0
    jumoo ·

    A hard constraint makes sense when it represents a genuine contractual date. The key is not to let it distort the schedule logic or hide the actual critical path and negative float.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?

Knowledge

Discussions

Norms