Critical Path DRAG

Critical path DRAG (Devaux’s Removed Activity Gauge) is a new scheduling metric in critical path analysis [[critical-path-method]]. It is the amount of time that an activity on the critical path [[critical-path]] (i.e., the longest path through the project) is adding to the project’s duration or, al

Started by Stephen Devaux ·
Last updated
Updated
Views
24 views

 

Critical path DRAG (Devaux’s Removed Activity Gauge) is a new scheduling metric in critical path analysis [[critical-path-method]].  It is the amount of time that an activity on the critical path [[critical-path]] (i.e., the longest path through the project) is adding to the project’s duration or, alternatively, the amount of time by which the project completion would be pulled in by reducing a critical path activity’s [[critical-activity]] duration to zero. 

Activities that are not on the critical path are said to have total float [[total-float]] or slack, i.e., the amount of time they can slip without making the project longer.  Conversely, only critical path activities and delays (such as lags or constraints) have DRAG.   

  1. DRAG can be computed in the following manner:
  2. If an activity has nothing in parallel, its DRAG is equal to its duration.

If an activity has other paths in parallel, its DRAG is whichever is less: its duration or the total float of the parallel activity with the least total float.

There are three commercially avaliable software packages that compute DRAG:

  • Spider Project.
  • PlanontheNet.com
  • Sumatra.com's Project Optimizer, which ias an add-on to Microsoft Project.

DRAG has a corollary cost effect called DRAG Cost [[DRAG-Cost]], which is the amount by which project profit is decreased due to an activity’s DRAG reducing the value of the deliverable and/or increasing project cost through indirect costs attached to level-of-effort activities or overhead. 