What is needed to come up with a production rate?A duration of time, the manhours involved, and an amount of work produced?This section is here to document this. What information do you have that you can share?
202 entriesSource page: Rates, Norms & Durations
Subjects on this page
| Activity | Entry (verbatim) | Value | Source |
|---|---|---|---|
| 005 Initiate PhaseIT Engineering Projects | — | 005 Initiate Phase | |
| 010 Analyse PhaseIT Engineering Projects | — | 010 Analyse Phase | |
| 015 Design PhaseIT Engineering Projects | — | 015 Design Phase | |
| 020 Develop PhaseIT Engineering Projects | — | 020 Develop Phase | |
| 025 Test PhaseIT Engineering Projects | — | 025 Test Phase | |
| 030 Implement PhaseIT Engineering Projects | — | 030 Implement Phase | |
| 035 Support PhaseIT Engineering Projects | — | 035 Support Phase | |
| Aluminium RoofingMetal Roof Decking | Aluminium Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Aluminium Work = 2.8 m2/day Sloping Roof Aluminium Work = 1.9 m2/day2 rate statements found; left for an editor | — | Aluminium Roofing |
| Asbestos Roofs Sheeted Roofs | Asbestos Type Roofs A typical rate of 39 m2/day | 39 m2 per dayper dayParsed | Asbestos Roofs |
| Asphalt RoofsFlat & Layered Roofs | Asphalt Roofs Usually carried out with a 2 man gang with an additional 1 or 2 labourers. A typical composite rate of 45 m2/day | 45 m2 per dayper dayParsed | Asphalt Roofs |
| Asphalt WaterproofingFacade Waterproofing | Asphalt coatings to prepared concrete surfaces, usually undertaken with a 3 man gang. Horizontal Surfaces = 210 m2/wk Vertical Surfaces = 85 m2/wk | — | Asphalt Waterproofing |
| Automotive | Automotive Production Rates & Build Times: | — | Automotive |
| Barrette PilesFoundation Works | Barrette PilesTask / DescriptionSlow Ave Fast Units Rule of Thumb, overall rate by Mill0.5 1.1 1.2 hrs/no Fabricate reinforcement cages- 4.0 - hrs/cage Concreting barrette panels40.0 50.0 55.0 m3/hr Trimming top of barrette panels- 2.4 - days/no Concrete Testing, Coring Test4.0 3.5 2.0 days/no Concrete Testing, Sonic Logging Test- 0.7 - days/no | 55 m3 per hrper hrParsed | Barrette Piles |
| Basement ExcavationBasement Excavations | Basement ExcavationTask / DescriptionSlow Ave Fast Units Hydraulic Excavator, 0.3m3 bucket, Sand/Soil - Basement Works6.4 8.0 9.4 m3/hr Hydraulic Excavator, 0.3m3 bucket, Gravel Beds - Basement Works5.5 6.9 8.1 m3/hr Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk - Basement Works5.2 6.5 7.9 m3/hr Hydraulic Excavator, 0.3m3 bucket, Hard Ground - Basement Works4.7 5.9 8.2 m3/hr Hydraulic Excavator, 0.4m3 bucket, Sand/Soil - Basement Works12.6 15.4 18.9 m3/hr Hydraulic Excavator, 0.4m3 bucket, Gravel Beds - Basement Works11.7 14.3 16.7 m3/hr Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk - Basement Works10.9 13.3 15.6 m3/hr Hydraulic Excavator, 0.4m3 bucket, Hard Ground - Basement Works9.7 11.8 14.0 m3/hr Hydraulic Excavator, 0.5m3 bucket, Sand/Soil - Basement Works18.2 20.0 23.0 m3/hr Hydraulic Excavator, 0.5m3 bucket, Gravel Beds - Basement Works16.5 18.1 20.0 m3/hr Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk - Basement Works15.4 16.7 19.3 m3/hr Hydraulic Excavator, 0.5m3 bucket, Hard Ground - Basement Works13.3 15.4 17.7 m3/hr12 rate statements found; left for an editor | — | Basement Excavation |
| Beam Falsework FormworkFormwork | Rates include for making, fixing, cleaning and minor repair works etc, rates in m2/hr.Soffits - On runners and props, including erection of props etc. Hight of Beam Soffit---> 0 - 3.5 m3.5 - 5.0 mWidthFixStrikeFixStrike 100 - 200 mm0.701.230.581.02200 - 300 mm0.811.390.681.15300 - 500 mm0.931.540.781.28500 - 750 mm1.161.850.961.54exc 750 mm1.232.171.031.82 Soffits - On runners and props, on previously erected props etc. Hight of Beam Soffit---> 0 - 3.5 m 3.5 - 5.0 mWidthFixStrikeFixStrike100 - 200 mm0.961.690.911.67200 - 300 mm1.111.921.051.82300 - 500 mm1.272.081.202.00500 - 750 mm1.562.501.492.44exc 750 mm1.642.861.392.70 Sides - Strutted from soffit bearers etc. Hight of Beam Soffit---> 0 - 3.5 m 3.5 - 5.0 mDepthFixStrikeFixStrike100 - 200 mm0.781.230.741.18200 - 300 mm0.931.390.881.32300 - 500 mm1.061.541.021.47500 - 750 mm1.472.081.392.00exc 750 mm1.542.331.472.33 Sides - Using clamps and struts etc. Hight of Beam Soffit---> 0 - 3.5 m 3.5 - 5.0 mDepthFixStrikeFixStrike100 - 200 mm0.911.470.871.39200 - 300 mm1.091.641.041.56300 - 500 mm1.271.821.201.72 | — | Beam Falsework Formwork |
| Bell Ground AnchorsEarthworks & Excavation | Bell Ground AnchorsTask / DescriptionSlow Ave Fast Units Uncased Anchors, 10m long- 2.0 - no/day Top Cased Anchors, 15m long- 1.0 - no/day Anchors stressing- 2.2 - no/day | — | Bell Ground Anchors |
| Bentonite WaterproofingFacade Waterproofing | Sheeting to be installed and covered over immediately in order to prevent drying out, carried out with a gang of at least 3 people. Horizontal Surfaces = 25.0 m2/hr Vertical surfaces = 15.0 m3/hr2 rate statements found; left for an editor | — | Bentonite Waterproofing |
| Bituminous WaterproofingFacade Waterproofing | Brush applied coatings (tretol etc) to prepared concrete surfaces. A two coat application = 5.0 m2/hr A three coat application = 3.5 m2/hr Sheet materials (bituthene etc) fixed to prepared concrete surfaces. Horizontal Surfaces = 4.0 m2/hr Vertical Surfaces = 3.5 m2/hr4 rate statements found; left for an editor | — | Bituminous Waterproofing |
| BlockworkBuilding & Construction | Blockwork | — | Blockwork |
| BlockworkWet Trade Finishes | — | Blockwork | |
| Bored PilingFoundation Works | Pre-Drilling - Site Investigation Pre-boring will be carried out at each location to ascertain the target founding level. Rotary rig drilling operations incorporate the use of a steel core that is used when a core sample is required. Another type of boreing is called “Wash Bore” or “Percussive Bore” which simply means that a bore is flushed out and is used when no soil sample is required. Typical rates are... Type of Strata Plant Used Rate (m/hr) Top soft deposits of site fill Percussive / Rotary 10.00 Grade V/IV rock deposits Wash Boring 3.15 Triple Tube Sampling 0.75 Grade III/II rock deposits Rotary 0.50 Triple Tube Sampling 0.50 With a standard rig, working a 12 hour shift, a typical output rate of 66 hrs/hole/rig is possible. As-Built Information. On Central Reclamation, Contract UA11/91, borehole drilling completed with the following results... Average depth of 61.15 m, total depth of 428 m Average rock socket depth of 4.65 m The durations ranged from 4 to 8 days Average of 5.85 days, total duration of 41 days. The Target Founding level This is defined as the required socket into the bedrock, which is defined as moderately decomposed rock grade III or better with a core recovery greater than 85% (allowable bearing capacity of 5 mPa). The continuity of the founding rock is demonstrated by continuing the pre-bored hole a maximum of 5 metres or 3 times the pile diameter, whichever is the greater. The cores are logged, stored and photographed and submitted together with proposed founding levels for approval. Setting Out Before starting excavation at the pile position the following steps are taken: Survey and record the existing ground level at the pile position Setout the pile location from the reference points and in order to monitor the position of the steel casing, control pins are usually established at two orthogonal positions, offset from the centre of the pile. Pile Tolerances In the case of out of position casings, adjustment can be made to keep the vertical alignment and plan position within the limits of no more than 75 mm off-centre on plan position and not deviating by more than 1:75 from the vertical axis. Pile Excavation / Casings The shaft of the pile is excavated within a temporary steel casing with an outside diameter of say approximately 200 - 300 mm greater than the pile diameter. The casing is used mainly in areas of unstable ground and are driven using hydraulic casing oscillator attached to a crawler crane or a casing vibrator. Shaft excavation is carried out using a single or double hammer grab supported by crawler crane. The steel casing toe is kept in front of the excavation level until it is 0.5 metres above the pile cut-of level. The pile shaft is often flooded with bentonite or water and excavation proceeds to the top of the CDG. Excavation then proceeds by reverse circulation drilling (RCD) using large diameter drilling heads with special rock cutters and flushing by air lift. Bentonite or water levels are always maintained above the ground water level to ensure stability of the shaft. Calculation Of Bored Pile Construction / Excavation Time Piling times can be reduced by the use of service cranes for reinforcement and concreting activities. An additional extended shift would often be required for certain piles, as would RCD down-time. Forecast construction times can be derived by using output rates (hours per item)... Operation Element Details Hours Add or Remove Reverse Circluation Drill Plant (RCD) incl drill bit 2 hrs Add or Remove RCD drill bit (incl assembly of drill string) 5 hrs RCD bell-out bit (incl drill string & stabilisers) 5 hrs Installation Airlift tremmie tube 5 hrs Reinforcement cages (time for joining each cage) 2 hrs Cleaning Time Initial airlift cleaning (after finishing excavation) 8 hrs Final airlift cleaning (after fixing steel cage) 2 hrs Concreting Incl extract casing ( < 70 m deep) 12 hrs ( > 70 and < 95 m deep) 14 hrs ( > 95 and < 135 m deep) 48 hrs Curing Time Only required prior to removal of telescopic casings 72 hrs Cycle Time Move piling setup to next location 2 hrs Shaft Excavation Strata Plant Used Rate (m/hr) General Fill (upper ground levels) Grab 3.50 m/hr Sand, Minor Rubble Grab 2.10 m/hr Marine / Alluvium Deposits Grab 2.50 m/hr CDG < 150 RCD/Grab 1.50 m/hr CDG > 150 < 200 RCD 1.00 m/hr CDG > 200, Compacted Gravel RCD 0.50 m/hr CDT RCD / Grab 0.50 m/hr Corestones RCD / Chisel 0.50 m/hr Rock Socket - Grade IV/V RCD 0.25 m/hr Rock Socket - Grade II/III RCD 0.125 m/hr Rock Socket - (Tendering Rate) RCD 0.10 m/hr Forecast excavation or cycle times can then be derived by analysing ground conditions. Site investigation will provide the depths / types of strata which can then be matched to production output rates (see above). Note - A pile’s diameter has negligible effect on production time and as such is ignored. Example - For a pile founding on rock at 60 m deep... (a) Calculate Allowance For Plant Time / Other Elements (hrs).... Element Hours Set up RCD 5.0 Excavate Time See Below Remove RCD (including drill bit, string and stabilisers) 5.0 Setup / Remove Airlift Tremmie Tube 5.0 Initial Post-Excavation Airlifting 5.0 Place reinforcement (5 No cages @ 12m = 5 x 2 hrs) 10.0 Setup / Remove Airlift Tremmie Tube 5.0 Final Post-Reinforcement Airlifting 2.0 Concrete and remove casing 12.0 Move to next location 2.0 Calculate Total Construction / Plant Time 52.0 hrs (b) Calculate Allowance For Excavation Time (hrs)... Depth of Strata (m) Type of Rock Production Rate (m/hr) Plant Used Time (Hrs) 0 - 20 Sand/minor rubble 2.00 Grab 10.0 20 - 35 CDG less than 150 1.50 RCD/Grab 10.0 35 - 47 CDG more than 150 1.00 RCD 12.0 47 - 57 CDG > 200/corestones 0.50 RCD 20.0 57 - 60 Rock socket 0.20 RCD 15.0 (c) Calculate Total Pile Excavation Time = 67.0 hrs (d) Overall Pile Time Construction / Plant Time (“b” above) 52.0 hrs Excavation Time (“d” above) 67.0 hrs OVERALL CYCLE TIME (“b” + “d”) 119 hrs (With 12 hr shifts) (“b” + “d”) 9.9 days Bored Pile Construction As-Builts General Rule of Thumb Pile Times (days)... Depth (m) => <20 <40 <70 <90 <135 Days Per Pile 4.0* 8.0 10.0 25.0 45.0 Note - due to the required plant assembly and operation times, 4 days is the minimum possible pile construction time for any situation. Methods For Overcoming Obstructions If the obstruction is shallow (ie 0 to 2.5 m below ground level) a backhoe-breaker will be used to form a suitable hole. Where the obstructions are located at greater depths an oversized temporary casing is driven by the oscillator to the top of the obstruction. If the obstruction is above water level a hand operated air hammer is used, a typical rate of = 0.8 m/hr If below water level a down the hole hammer or heavy chisel supported by crawler crane will be used, a typical rate of = 0.5 m/hr If a concrete “plug” is required to provide a well formed shaft wall when an obstruction or excessive overbreak or fault is encountered... Element Hours Remove RCD 5 hrs Install Tremie Concrete Tube 5 hrs Place Concrete Plug 2 hrs Cure Concrete 36 hrs Replace RCD and drill string 5 hrs TOTAL TIME LOSS 53 hrs (2.2 days or 4.4 shifts) Cleaning of Pile Base The hole of the pile shaft is cleaned using an airlift until the water becomes clean or negligible particles in suspension is discharged. Reinforcement Cages Cages are constructed in suitable sections, usually in the order of 12 m long, complete with sonic tubes and coring tubes. Fabrication, 12 m long cage with 6 no fixers... Fabricate 1 cage 2.5 hrs Total cages required 5 no Overall Fabrication Time 12.5 hours Steel Stanchion Fabrication and Installation Stanchions are usually fabricated off-site and delivered in sections. Prior to installation the sections are welded together to form the complete stanchion. Stanchion sizes are usually in the region of 525 mm x 525 mm. With an average length of say 28 m, the welding time would be around 5 days and are tested by an ultrasonic weld test and an MPI test. After the installation of the reinforcing cage in to the shaft the stanchion will be lifted until it hangs vertical. It is then lowered into the excavation and clamped into position. Concreting Pile concreting is carried out under water by "tremie" techniques maintaining the water or bentonite head inside the casing at or above existing ground water level. The tremie tube (250mm) is withdrawn as concreting proceeds ensuring a minimum concrete head of 2 metres above the top of the tremie tube. Sequence Of Piling The sequence of construction of piles is chosen in such a manner that no damage can be caused to nearby piles still under construction or recently concreted (i.e. less than 3 days). On a 12 metre grid, a normal layout would mean say having two non-worked on piles between each open excavation in the longitudinal direction (ie a 36 metre spacing) thus allowing room for the crane etc and a lesser spacing of every other pile being worked on (ie a 24 metre spacing). Pile Testing The workability of concrete is tested on site by measuring the slump and temperature of concreting at the time of discharge into the pile shaft. Laboratory tests are carried out in order to check the strength of the placed concrete. A number of test cubes are made and tested at 7 and 28 days. Coring Test - Certain piles selected by the Engineer will be cored their full depth. The depth of cores into the base material (rock) will usually be at least 600 mm. Cores are placed in correct order and relative position in core boxes which clearly mark the depths of cores. The cores are usually photographed and submitted to the Engineer. The testing of the coring will provide additional information about the quality of the concrete as well as the condition of the interface between concrete and rock. Sonic Logging Test - In order to test the quality of the concrete as well as the integrity of the pile in its overall length and pile toe condition sonic core testing is used. Sonic tubes are installed with the reinforcement cage in order to allow the lowering of the signal transmitter and signal receiver probe down the bottom of the pile. These tubes are sealed at the bottom. Vibration Tests - This test determines the pile length and shape and the overall pile concrete quality. This is a specialist test.13 rate statements found; left for an editor | — | Bored Piling |
| Bored PilingEarthworks & Excavation | Bored PilingTask / DescriptionSlow Ave Fast Units Cycle Time, 5-20m deep8.0 4.0 4.0 days/no Cycle Time, 20-40m deep10.0 8.0 - days/no Cycle Time, 40-70m deep25.0 10.0 - days/no Cycle Time, 70-90m deep45.0 25.0 - days/no Cycle Time, 90-135m deep60.0 45.0 - days/no Move piling setup to next location- 2.0 - hrs Excave shaft by grab, general fill/uppr levels- 3.5 - m/hr Excave shaft by grab, sand/minor rubble- 2.1 - m/hr Excave shaft by grab, marinve/aluvium- 2.5 - m/hr Excave shaft by grab/RCD, CDT- 0.5 - m/hr Excave shaft by grab/RCD, CDG <150- 1.5 - m/hr Excave shaft by RCD, CDG 150-200- 1.0 - m/hr Excave shaft by RCD, CDG >200/gravel- 0.5 - m/hr Excave shaft by RCD/Chisel, corestones- 0.5 - m/hr Excave Rock Socket by RCD, grade IV/V rock- 0.2 0.3 m/hr Excave Rock Socket by RCD, grade II/III rock- 0.1 0.2 m/hr Excave Rock Socket by RCD, tendering rate- 0.1 - m/hr Add/remove RCD plant- 2.0 - hrs Add/remove RCD drill string/drill bit- 5.0 - hrs Remove Obstruction, above water hand hammers- 0.8 - m/hr Remove Obstruction, below water heavy chisel- 0.5 - m/hr Concrete Plug, RCD off/tremmie/concrete/cure/RCD on60.0 53.0 50.0 hrs Install air lift tremmie tube- 5.0 - hrs Fabricate reinforcement cages- 2.5 - hs/cage Install reinforcement cages- 2.0 - hrs/no Shaft cleaning, air lifting after excavation- 8.0 - hrs Shaft cleaning, air lifting after cage installed- 2.0 - hrs Shaft concreting/extract casing 5-70m deep- 12.0 - hrs Shaft concreting/extract casing 70-95m deep- 14.0 - hrs Shaft concreting/extract casing 95-135m deep- 48.0 - hrs Concrete curing prior to remove telescopic casing- 72.0 - hrs Concrete Testing, Coring Test- 3.2 2.2 m/hr Concrete Testing, Sonic Logging Test- 2.5 - hrs/no Concrete Testing, Vibration Test- 6.5 - hrs/no3 rate statements found; left for an editor | — | Bored Piling |
| Breaking OutBreaking Out & Openings | Concrete And Remove (hrs/m3) DepthHandMachineSlabs - unreinforcedNe 50 mm2.351.96 50 - 100 mm3.152.46 100 - 200 mm3.753.94 200 - 300 mm4.125.55Slabs - reinforcedNe 50 mm4.713.92 50 - 100 mm5.524.32 100 - 200 mm5.884.71 200 - 300 mm6.129.09Walls - unreinforcedall walls4.713.04Walls - reinforcedall walls5.523.92Beams - reinforcedall sizes7.505.89Columns - reinforcedall sizes9.207.30Foundations - unreinforcedall sizes3.603.00Foundations - reinforcedall sizes5.404.80 Breaking Out TarmacRates include for breaking out and removal of rubble (hrs/m3). DepthHandMachinePavingsNe 50 mm1.961.56 50-100 mm2.081.64 100-150 mm2.171.75Roadwaysupto 150 mm 3.57 Breaking Out BrickworkRates include for breaking out and removal of rubble (hrs/m3). DepthHandMachineWalls/columnsNe 100 mm2.401.38 exc 100 mm2.751.57Foundationall sizes2.751.57Breaking Diaphragm WallBreaking Openings using coring machine 0.2m3/hourBreaking out to expose couplers using hand held braker 1.75m2/day ot 2.5m run/day (0.7m slab) Task / DescriptionSlow Ave Fast Units Concrete Slabs, unreinforced 50-150mm3.2 - 1.9 hrs/m3 Concrete Slabs, unreinforced 150-300mm5.5 4.1 3.7 hrs/m3 Concrete Slabs, reinforced 50-150mm5.2 - 3.9 hrs/m3 Concrete Slabs, reinforced 150-300mm9.1 6.2 4.7 hrs/m3 Concrete Walls, unreinforced4.7 3.9 3.1 hrs/m3 Concrete Walls, reinforced5.6 4.7 3.9 hrs/m3 Concrete Foundations, unreinforced3.6 3.3 3.0 hrs/m3 Concrete Foundations, reinforced5.4 5.1 4.8 hrs/m3 Concrete Beams7.5 6.5 5.6 hrs/m3 Concrete Columns9.2 8.2 7.3 hrs/m3 Tarmac paving 20-50mm thick1.9 1.7 1.5 hrs/m3 Tarmac paving 50-100mm thick2.1 - 1.6 hrs/m3 Tarmac paving 100-150mm thick2.1 - 1.7 hrs/m3 Tarmac roadway 150mm thick- 3.6 - hrs/m3 Brickwork, walls and columns2.4 1.8 1.3 hrs/m3 Brickwork, foundations2.7 2.1 1.5 hrs/m32 rate statements found; left for an editor | — | Breaking Out |
| BrickworkExternally | Output 25m2 per man week overall facing brickwork | 25 m2 per man weekper man weekParsed | Brickwork |
| Bridge Items - Work Activity Base Production Rates in USABridges | Work Activity Base Production RatesItemUnitBase RateMetric Base Rate Grade Items MobilizationDays5 Clearing & GrubbingAcres31 Demo. Of BuildingsEach1 Asbestos Rem.(Res./Small Commercial)Days4 Asbestos Rem.(Large Commercial)Days10 Demo. Of Asphalt Pave.S.Y.15001254 Sawcut PavementL.F.800244 Remove Curb& GutterL.F.600183 Remove Exist. DI/Manhole & Assoc. PipeEach6 Temporary DetourDays6 Roadway ExcavationC.Y.20001529 Excavation Small/Irregular Area ProjectsC.Y.850650 Excavation - Large quantity projectsC.Y.50003823 Drainage Corrug.Metal 18"L.F.20562 Drainage Concrete Pipe 15"L.F.16851 Drainage Conc. Pipe 18"L.F.14444 Drainage Conc. Pipe (24" to 54")L.F.7222 Drainage Conc. Pipe (60 in. & greater)L.F.4815 Base Rate Adjustment Factors Inlets/ManholesEach2 Minor Excavation (Drainage Structures)C.Y.250191 Box Culverts, Class A Conc.C.Y.2015FactorsAdjustment for Noted Conditions Box Culverts, Cast in PlaceL.F.52LocationRural = 1.0Small City = 0.85Big City = .75 Box Culverts, PrecastL.F.206Traffic ConditionsLight = 1.0Moderate = .88High = .70 Retaining Walls, Cast in PlaceL.F.52ComplexityLow = 1.0Medium = .85High = .70 Major Retaining WallsS.F.21020Soil ConditionsGood = 1.0Fair = .85Poor = .65 Sub-grade StabilizationS.Y.80006689Quantity of WorkLarge = 1.0Medium = .88Small = .75 Aggregate BaseTons13601234 Aggregate Base Small/Irregular ProjectsTons680617 Drainage BlanketTons12001089Example Production Rate Calculation for Roadway Excavation: Asphalt BaseTons11751066Conditions: Rock Excavation around moderate traffic. Asphalt IntermediateTons750680Calculation: 2000 C.Y. x .65 x .88 = 1144 C.Y. per day Asphalt SurfaceTons500454 Milling/Flexible Pavement Planing (Max. 2")S.Y.30002509 Curb & Gutter (Machine Placed)L.F.800244Example Production Rate Calculation for Bridge Footing: Curb & Gutter (Hand Placed)L.F.400122Conditions: Rural Bridge Replacement, Traffic Detoured, Small Two Lane structure Curb& Gutter Radial (Hand Placed)L.F.15046Calculation: 20 C.Y. x 1.0 x .75 = 15 C.Y. Concrete EntranceS.Y.8067 SidewalkS.F.1550144 Concrete DrivewayS.Y.150125 Entrance PavementS.Y.10084 Barrier Walls, Slip FormL.F.630192 Concrete RepairS.Y.3025 Concrete PavingS.Y.25002090 Slurry SealS.Y.80006689 SeedingAcres2.51 FencingL.F.1000305 Fine GradingS.Y.20001672Assumptions/Notes: Lime StabilizationS.Y.60005017 Shoulder ConstructionL.F.500152 Slope ProtectionC.Y.10076A.) Production rates are units/day based on an 8 hr. day unless otherwise noted, UnderdrainL.F.1500457such as by Days or POUR. Underdrain Outlet/EndwallEach8 Utility 12" Ductile IronL.F.10532B.) Production rates are based on the average of rates from five other nearby states with Utility 12" PVCL.F.32098assumed similar work conditions. States referenced were Kentucky, Tennessee, Directional DrillingL.F.5015New Jersey, West Virginia, and Georgia. Traffic Items ItemUnitBase RateMetric Base Rate Initial Traffic ControlDays2 C.) RS Means Rates and VDOT records were also used as a reference when wide variation Ordering Signal Equip.Days30 was found between different state's rates or if little information was available for a specific Major Traffic SignalsDays/Intersec.40 work item. Pavement MarkingsL.F.10,0003048D.) Scheduler should contact Roadside Development for planting restrictions and time Stop Bars, etc.L.F.500152estimates. Landscaping rates are typically controlled by the planting season. Arrows/LettersEach50 Order Sign MaterialDays60 E.) Production rates were verified by VDOT project records as much as possible and are Order Overhead Sign Struct.Days80 intended for temporary use until the final database is produced at the conclusion of Erecting Overhead SignsDays10 a more intensive three year study of historical data specific to VDOT. Erecting SignsS.F.100093 Ordering Lighting MaterialDays60 F.) Sensitivity Factors are estimated according to their effect on normal production. Erecting LightingDays/support3 If the scheduler disagrees with the factors for a specific application, he or she should GuardrailL.F.1500457develop a unique value. For example excavation rates will be widely variable Guardrail TerminalsEach2 considering the range of topography between the Bristol and Hampton Road Districts. Order Impact AttenuatorsDays30 If the average figure sounds off for your project, consider making additional calculations Install Impact AttenuatorEach3 based on the excavation equipment most likely to be used. Electrical ConduitL.F.400122 Electrical WireL.F.35001067 Precast concrete barrierL.F.800244G.) Utility 12" and drainage pipes include excavation/backfill for good soil conditions in a 4-5 ft.+/- Lighting, Total Installation Lumin.Each2 trench. Additional time for excavation should be estimated by the scheduler Phasing AllowanceDays/Phase3 for unfavorable conditions. Bridge Items H.) Several of the adjustment factors should have similar impacts on production, ItemUnitBase RateMetric Base Rateso generally it is recommended not to reduce the base quantity by more than 2 factors except MOT Setup in special circumstances. Impact AttenuatorsEA2.0 Median Barrier - InstallLF800.0244I.) Consult with your Traffic Engineering Section for production rates for specialty Removing Exst. GuardrailLF1500.0457items to make sure you account for the necessary review and fabrication times. Shoulder ImprovementsLF500.0152 Signs, Install Small (Sheet)EA30.0 Temporary Detour Bridge - InstallDays13.0 Traffic Control SetupDays2.0 Excavation/Demolition CofferdamDays15.0 Dismantle/Remove Exst. Concrete DeckSY275.0230 Dismantle/Remove Exst. StructureSY50.042 Minor ExcavationCY250.0191 Sheet Piling - DriveSF500.046 Structure ExcavationCY300.0229 CBR30 Backfill/Compact AbutmentTON100.091 Substructure Items Drilled ShaftsEA0.3 Epoxy Injection Crack RepairLF80.024 Reinforcing SteelTON2.52 Retaining Walls (CIP)SF400.037 Riprap - DumpedTON700.0635 Riprap - GroutedTON50.045 Riprap - Machine PlacedTON250.0227 Slope Protection - ConcreteSY750.0627 Steel Piles - PreboredLF250.076 Steel Piles - DrivenLF400.0122 Concrete Piles - 8" to 14"LF300.091 Concrete Piles - 24" to 30"LF325.099 Substructure Footings - Form and PlaceCY20.015 Substructure Neatwork - Form and PlaceCY10.08 Substructure Footing - Place SealCY15.011 Superstructure Items Approach SlabsDAY5.0 Beam Repairs - Concrete Beam EndEA0.3 Beam Repairs (Steel) - BoltedEA0.5 Beam Repairs (Steel) - WeldedEA1.0 Bridge Deck - Form & Place Reinf. SteelSY50.042 Bridge Deck - OverlaySY500.0418 Bridge Deck - Pour NewSY850.0711 Bridge Deck GroovingSY550.0460 Bridge Deck - Sidewalk/Raised MedianLF80.024 CIP Conc. Slab Span - Install FalseworkSF250.023 CIP Conc. Slab Span - PourCY10.08 Concrete Diaphragms - Form & PourCY11.08 Concrete Removal - Sub/Super PatchSY15.013 Concrete Removal - Type B PatchSY50.042 Concrete Removal - Type C PatchSY10.08 Concrete Surface Color CoatingSY100.084 Expansion DamEA4.0 Expansion Joint ReconstructionLF25.08 Expansion Joint RemovalLF250.076 Expansion Joint SealerLF450.0137 Milling (Concrete - per 1/2" depth)SY1600.01338 Parapet - Hand FormedLF50.015 Parapet - Slip FormedLF200.061 Metal Rail ParapetLF100.030 Kansas Corrall ParapetLF20.06 Pedestrian FenceLF7.02 Prestressed Conc. Beam ErectionLF400.0122 ShotcreteSY65.054 Struct. Steel Surface Prep. (Method 1)SF3000.0279 Struct. Steel Surface Prep. (Method 2)SF240.022 Struct. Steel Surface Prep. (Method 3)SF600.056 Struct. Steel Surface Prep. (Method 4)SF200.019 Struct. Steel Surface Prep. (Method 5)SF1100.0102 Struct. Steel Surface Prep. (Method 6)SF6000.0557 Struct. Steel Surface Prep. (Method 7)SF7500.0697 Structural Steel - Painting (per coat)SF2000.0186 Structural Steel ErectionTON10.09 Structural Steel ErectionLF200.061 Timber Bridge DeckSF200.019 Finishing Items/MOT Teardown CIP Conc. Slab Span - Remove FalseworkSF500.046 Median Barrier - RemoveLF800.0244 Sheet Piling - PullSF500.046 Temporary Detour Bridge - RemoveDays4.0 Traffic Control TeardownDays2.0 Concrete Curing Cure days/Pour Item Cure days/Pour Deck overlays - Assume 20 CY of material placement per day LMCPOUR5 HESLMCPOUR3 VESLMCPOUR1 New Construction Substructure FootingsPOUR2 Substructure NeatworkPOUR5 Bridge Deck ConcretePOUR7 ParapetPOUR7 Component Level Production Rates(Recommended for use at Field Inspection before all quantity details are known) ItemUnit#Days Special Notes: AbutmentsDays8 Add 1 day for each 400' of piles. Add time for cofferdam/structure exc. Includes normal curing conditions.Piers or BentsDays15 Add 1 day for each 400' of piles. Add time for cofferdam/structure exc. Includes normal curing conditions.Concrete Deck Span 20'-40'Days15 Includes form, rebar, pour, normal cure time. Concrete Deck Span 41'-60'Days21 Includes form, rebar, pour, normal cure time. Concrete Deck Span 61'-80'Days27 Includes form, rebar, pour, normal cure time. Concrete Deck Span 81'-100'Days33 Includes form, rebar, pour, normal cure time. Concrete Deck Span 101'-120'Days39 Includes form, rebar, pour, normal cure time. Concrete Deck Span 121'-140'Days45 Includes form, rebar, pour, normal cure time. Steel Beams (Plate Girder)Each Add 2-3 days/span for diaphragms Steel Beams (Rolled Steel)Each Add 1 day/span for diaphragms Concrete BeamsEach Add 2-3 days/span for diaphragms New Bridge ConstructionL.F. 1 station (100 ft.) of 12 ft. lane roadway rural or new constructionDays2 Includes clearing & grubbing, grading, pavement structure, guardrail, seeding, and light drainage work. 1 station (100 ft.) of 12 ft. lane roadway urban or widening workDays4 Includes above plus curb & Gutter, Drainage, Utilities, and items commonly encountered in urban work. Note: Component Level Production Rates are recommended for estimating time at the field inspection or early planning stages before quantities are known. | — | Bridge Items - Work Activity Base Production Rates in USA |
| Bulk ExcavationEarthworks & Excavation | Bulk ExcavationTask / DescriptionSlow Ave Fast Units Excavation Bulking Factor, Sand/Soil- 15.0 20.0 % Excavation Bulking Factor, Gravel- 33.0 - % Excavation Bulking Factor, Clay/Chalk- 40.0 - % Excavation Bulking Factor, Boulder Clay- 45.0 - % Excavation Bulking Factor, Rock- 60.0 - % Spoil Weight, Rock- 2.5 - Tonnes/m3 Spoil Weight, Concrete- 2.4 - Tonnes/m3 Spoil Weight, Landfill/CDG- 1.9 - Tonnes/m3 Spoil Weight, Sand- 1.8 - Tonnes/m3 Rail Mounted Grab, 2.0m3 bucket 2.4min lift cycle30.0 48.0 59.0 m3/hr Crane Mounted Clamshell Grab, 2.0m3 bucket 2.9min lift cycle25.0 33.0 41.0 m3/hr Crane Mounted Clamshell Grab, 2.5m3 bucket 2.9min lift cycle34.0 42.0 52.0 m3/hr Hydraulic Excavator, 0.3m3 bucket, Sand/Soil6.9 8.7 10.2 m3/hr Hydraulic Excavator, 0.4m3 bucket, Sand/Soil23.4 28.6 33.4 m3/hr Hydraulic Excavator, 0.5m3 bucket, Sand/Soil45.5 50.0 58.0 m3/hr Hydraulic Excavator, 0.3m3 bucket, Gravel Beds5.6 7.1 8.2 m3/hr Hydraulic Excavator, 0.4m3 bucket, Gravel Beds20.5 25.0 29.0 m3/hr Hydraulic Excavator, 0.5m3 bucket, Gravel Beds36.8 40.0 46.0 m3/hr Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk5.6 7.1 8.3 m3/hr Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk20.5 25.0 28.7 m3/hr Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk37.0 40.0 46.0 m3/hr Hydraulic Excavator, 0.3m3 bucket, Hard Ground4.5 6.1 7.2 m3/hr Hydraulic Excavator, 0.4m3 bucket, Hard Ground17.9 22.2 25.0 m3/hr Hydraulic Excavator, 0.5m3 bucket, Hard Ground25.7 28.6 32.9 m3/hr15 rate statements found; left for an editor | — | Bulk Excavation |
| Cable CarTransportation | The 21 months duration for the 14km cable car project from the land available date is made up of the following activities:5 months lead time to the mast foundation contract before the cable car contractor can get access to the foundation for a 10 months installation works. The cable car contractor's installation is followed by the last 2 months of their overall 6 months testing and commissioning. This is then followed by a 4 months of Test & Trial Running. The 27 months programme of cable car's manufacturing, delivery, installation and test and commissioning is based on the extract of the supplier's programme. | — | Cable Car |
| Cable StringingBridges | — | Cable Stringing | |
| Carpentry & JoineryFitout & Finishes | Carpentry & JoineryTask / DescriptionSlow Ave Fast Units Formwork to Soffit of Manhole- 1.8 - m2/hr Formwork to Walls of Manhole11.2 14.2 20.2 m2/hr Formwork to Road Edges, straight- 7.7 - m/hr Formwork to Road Edges, curves- 6.2 - m/hr | 20.2 m2 per hrper hrParsed | Carpentry & Joinery |
| Carpentry CarcassingFitout & Finishes | Carpentry CarcassingTask / DescriptionSlow Ave Fast Units Windows, Timber Frames for Bricklaying1.1 0.5 0.1 hrs/no Windows, Drill, Screw & Plug extra over0.3 0.1 - hrs/no Door Frames, Softwood, 1.0-3.0m2- 0.2 - hrs/no Door Frames, Softwood, 3.0-7.0m20.5 0.4 - hrs/no Door Frames, Softwood, 7.0-10.0m21.2 0.8 - hrs/no Door Frames, Hardwood, 1.0-3.0m2- 0.3 - hrs/no Door Frames, Hardwood, 3.0-7.0m20.6 0.3 - hrs/no Door Frames, Hardwood, 7.0-10.0m21.4 1.0 - hrs/no Erect Water Tank Platform- 2.3 - no/hr Fix Studding For Bath- 0.1 - hrs/m Cut Access Hatch- 0.3 - no/hr Floor Joists, under 3m9.0 9.6 11.6 no/hr Floor Joists, 3.0-4.5m6.8 7.2 9.7 no/hr Floor Joists, 4.5-6.0m5.5 5.8 7.3 no/hr Ceiling Joists, under 3m12.8 14.0 14.7 no/hr Ceiling Joists, 3.0-4.5m10.8 12.1 12.6 no/hr Ceiling Joists, 4.5-6.0m9.6 10.8 11.1 no/hr Ceiling Joists, Notch to Beams20.0 25.0 28.5 no/hr Ceiling Joists, Pack Joist Ends20.1 23.8 26.3 no/hr Ceiling Joists, Nailing Joists together- 23.0 - m/hr Ceiling Joists, Bolting Joists Together- 12.6 - m/hr Floor Boards, Butt Jointed- 1.7 - m2/hr Floor Boards, T&G Boards, under 75mm wide- 3.4 - m2/hr Floor Boards, T&G Boards, 75-100mm wide- 3.8 - m2/hr Floor Boards, T&G Boards, 100-125mm wide- 4.2 - m2/hr Floor Boards, T&G Boards, 125-150mm wide- 5.5 - m2/hr Plywood Sheeting, Butt Jointed, nailed- 9.1 10.2 m2/hr Plywood Sheeting, Butt Jointed, screwed- 4.1 4.8 m2/hr Plywood Sheeting, T&G Jointed, nailed- 8.3 9.1 m2/hr Plywood Sheeting, T&G Jointed, screwed- 4.0 4.6 m2/hr Chipboard Sheeting, Butt Jointed, nailed- 10.0 11.5 m2/hr Chipboard Sheeting, Butt Jointed, screwed- 5.1 5.8 m2/hr Chipboard Sheeting, T&G Jointed, nailed- 9.3 9.1 m2/hr Chipboard Sheeting, T&G Jointed, screwed- 5.5 5.9 m2/hr16 rate statements found; left for an editor | — | Carpentry Carcassing |
| Carpentry Final FixingFitout & Finishes | Carpentry Final FixingTask / DescriptionSlow Ave Fast Units Windows, Softwood, 3.0-7.0m20.6 0.4 0.3 hrs/no Windows, Softwood, 7.0-10.0m21.3 0.9 0.6 hrs/no Windows, Hardwood, 1.0-3.0m20.4 0.3 - hrs/no Windows, Hardwood, 3.0-7.0m20.7 0.5 0.4 hrs/no Windows, Hardwood, 7.0-10.0m21.6 1.2 0.7 hrs/no Windows, Aluminum, 1.0-3.0m20.2 0.3 - hrs/no Windows, Aluminum, 3.0-7.0m20.5 0.4 0.3 hrs/no Windows, Aluminum, 7.0-10.0m21.2 0.8 0.5 hrs/no Windows, Steel, 1.0-3.0m20.4 0.3 0.2 hrs/no Windows, Steel, 3.0-7.0m21.2 0.6 0.5 hrs/no Windows, Steel, 7.0-10.0m21.4 1.2 1.0 hrs/no Window Boards, nailed- 0.3 0.2 hrs/m Window Boards, screwed- 0.4 0.3 hrs/m Mouldings, Softwood, Nailed- 6.3 8.5 m/hr Mouldings, Softwood, Screwed- 4.6 5.6 m/hr Mouldings, Softwood, Gun Nailed- 8.2 11.1 m/hr Mouldings, Hardwood, Nailed- 3.3 5.5 m/hr Mouldings, Hardwood, Screwed- 2.4 3.7 m/hr Mouldings, Hardwood, Gun Nailed- 8.5 11.3 m/hr Skirting, Aluminum, Screwed 150-300mm centres- 7.6 - m/hr Skirting, Aluminum, Screwed 300-450mm centres- 4.5 - m/hr Skirting, Plastic, Adhesive Fixing- 8.6 - m/hr Architrave Mouldings9.5 12.2 18.2 m/hr Architrave, Fix to Doors- 1.2 - hrs/door Door Stop Mouldings10.1 16.9 25.0 m/hr Glazed Bead Mouldings15.5 18.6 20.4 m/hr Hanging Doors, Softwood, Single Pair Butts1.3 0.9 0.6 hrs/no Hanging Doors, Hardwood, Single Pair Butts1.9 1.2 0.9 hrs/no Cut Mortice to Receive Lock, Softwood- 0.2 - hrs/no Cut Mortice to Receive Lock, Hardwood- 0.6 - hrs/no Cut & Fix Formica Bath Panel- 0.4 - hrs/no Kitchen Cupboards, Floor Units- 0.8 0.6 hrs/no Kitchen Cupboards, Wall Units- 0.7 0.5 hrs/no Kitchen Cupboards, Shelf Units- 0.8 0.7 hrs/no Staircase, pre-made, simple, straight flight1.9 1.5 1.1 hrs/no Staircase, pre-made, 2 straight flights, 1 landing3.7 2.9 2.6 hrs/no Staircase, pre-made, 2 straight flights, 2 landings- 6.3 - hrs/no Staircase, Balustrades/Handrails, fix horizontal1.2 0.6 0.1 hrs/no Staircase, Balustrades/Handrails, fix raking0.9 0.5 0.3 hrs/no Staircase, Cut and Fix Newel to Walls0.9 - 0.2 hrs/no Windows, Softwood, 1.0-3.0m20.3 0.2 - hrs/no Raised Flooring, metal system- 0.5 - m2/hr9 rate statements found; left for an editor | — | Carpentry Final Fixing |
| Ceiling FinishesFitout & Finishes | Ceiling FinishesTask / DescriptionSlow Ave Fast Units Suspended Ceilings, office situations- 2.6 3.5 m2/hr Suspended Ceilings, First Fix- 0.7 - m2/hr Suspended Ceilings, Second Fix- 1.2 - m2/hr | 3.5 m2 per hrper hrParsed | Ceiling Finishes |
| CeilingsPainting & Decorations | Emulsion paint - 2 coat 6.05 m2/hr - 3 coats 5.02 m2/hr Textured paint 4.20 m2/hr Artex 4.10 m2/hr4 rate statements found; left for an editor | — | Ceilings |
| Cladding RestorationFacade Waterproofing | Brickwork Restoration = 6.5 m2/day Stonework Restoration = 20.0 m/day (single course)2 rate statements found; left for an editor | — | Cladding Restoration |
| Cofferdam WorksDewatering | Soil Mix Wall Three auger machine drilling and mixing cement into three cores. H-piles dropped into two, then machine moves along by two holes. An average output was 4 - 5 m/day. | — | Cofferdam Works |
| Common BrickworkCutting Holes | Common Brickwork, by Machine (no/hr) Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500 Ne 100 cm2 - 16.6 7.69 5.26 4.00 100-250 cm2 - 12.5 5.88 4.00 2.94 250-500 cm2 - 10.0 5.00 3.33 2.50 500-100 cm2 - 8.33 4.17 2.78 2.08 Common Brickwork, by Hand (no/hr) Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500 Ne 100 cm2 11.1 8.33 5.56 3.85 - 100-250 cm2 9.09 7.14 4.55 3.23 - 250-500 cm2 7.69 5.88 3.85 2.70 - 500-100 cm2 6.67 4.76 3.23 2.27 - | — | Common Brickwork |
| Compact & ConsolidateGround Compaction | Compact & Consolidate using Vibratory Roller or compactor. Sand 31.25 m2/hr Soil 58.82 m2/hr Clay 55.56 m2/hr Hardcore 38.46 m2/hr Ash 57.85 m2/hr5 rate statements found; left for an editor | — | Compact & Consolidate |
| Computer Room / Raised FloorsBuilding & Construction | Typically installed by a 2 man gang Medium sized room incl cutting 2.67 m2/hr | 2.67 m2 per hrper hrParsed | Computer Room / Raised Floors |
| Concrete FinishingPlacement & Finishing | Concrete FinishingTask / DescriptionSlow Ave Fast Units Surface Finishing, Steel Float By Hand9.2 13.9 25.0 m2/hr Surface Finishing, Wood Float By Hand11.7 17.2 29.4 m2/hr Surface Finishing, Power Float13.9 20.8 37.0 m2/hr Surface Finishing, Light Brush on Trowel55.8 90.1 170.0 m2/hr Surface Finishing, Brush on Trowel Margin28.8 48.5 85.0 m2/hr Surface Finishing, Sprayed By Pump, expose aggregate65.0 95.0 145.0 m2/hr Surface Finishing, Wire Brush, expose aggregate15.0 25.0 30.0 m2/hr Making Good Walls, prepare, shutter, pour- 5.5 8.6 m2/hr Making Good Columns, prepare, shutter, pour- 2.8 6.9 m2/hr Making Good Sides of Beams, prepare, shutter, pour- 2.8 7.0 m2/hr Making Good Slab Soffits, prepare, shutter, pour- 4.2 5.5 m2/hr Making Good Bolt Holes, prepare, shutter, pour14.8 16.8 25.8 no/hr Making Good Rubdown Precast Concrete, prepare, shutter, pour- 18.0 - m2/hr Making Good Scabble 3 head brush hammer, prepare, shutter, pour30.7 59.5 73.8 hrs/m212 rate statements found; left for an editor | — | Concrete Finishing |
| Concrete PumpingPlacement & Finishing | Large Concrete Pours, lorry pump. Simple Rule Of Thumb, concretors 0.5 - 1.0 hrs/m3 of concrete, depending on access, pour size and concrete availability. Base Slabs etc, 1,200m3 equalling 25 - 35m3/hr per pump, with 3 No pumps and 12 men for 2 shifts of 12 hrs. | — | Concrete Pumping |
| Concrete Road surfacingRoad Surfaces | Task / DescriptionSlow Ave Fast Units Concrete Road surfacing, Kerbs or Side Haunches- 0.4 - m3/hr Concrete Road surfacing, 150mm thick- 12.5 - m2/hr Concrete Road surfacing, 200mm thick- 7.7 - m2/hr Concrete Road surfacing, 300mm thick- 6.7 - m2/hr | — | Concrete Road surfacing |
| Cone Fracture Rock BreakageChemical Excavation Methods | Penetrating Cone Fracture Rock Breakage. Tradename of "SunBurst" from Australia. State of the art, non-explosive chemical rock breakage technology for close proximity excavation applications in mining and civil engineering. Explosive system, cycle time of 6 mins, giving 0.33 m3 each explosion. A typical rate of 10 No cycles per hour, giving 3.3 m3/hr/rig. However, tests have shown differing results... Fresh granite of class 1 strength - One hole in the floor, yielding 0.15 m3 of rock. If more holes had been injected, a yield of 0.5 - 1.0 m3 would be expected. Moderately fresh igneous rock of class 2 strength - Three holes in a sloping trench, in adjacent locations, yielding 2.6 m3 of rock for each hole. Moderately weathered volcanic rock of class 3 strength - Two holes in the floor, in separate locations, yielding 1.2 - 1.5 m3 of rock for each hole. | 3.3 m3 per hrper hrParsed | Cone Fracture Rock Breakage |
| Construction DesignPreparation Works | — | Construction Design | |
| Contigous PilingFoundation Works | Principles of Construction Often known as "Colcrete" piling, which is a type of trade name. Usually replaced by diaphragm walling methods.Essentially typical bored piles, or down-the-hold bored piles, are constructed with a spacing such that each pile is virtually touching the next. These are constructed on a hit-and-miss basis.After a suitable length of these piles are in place (often 9 piles or so) a smaller drilling rig follows on behind placing the "colcrete" piles. A small diameter shaft, often 100 mm or so, is drilled on the external face of the pile wall close to the interection between the two main piles. This excavated pile is fitted with a grout tube and backfilled with gravel. The pile is then grouted and forms a seal between the adjacent piles. This type of pile wall can be constructed with either a standard reinforcement cage or a "H" pile.Info below achieved on project in Bermonsey, London - Sept 2010 1 rig, 600dia contig piles, 12-15m deep, 12No per day (average), 15No per day (max)Rule of thumb based on Hit 1, Miss 3 = 8.5l/m day per rig.Labour: 1 Rig driver, 1 banksman, 1 conc pump operative, 3 x steel fixers, 1 x 360 driverPlant: 1x rig, 1x mini 360 exc, 1x 6m3 mixer, 1x pump, - Deliveries: 4 - 5No 6m3 wagons per rig per day (av 2m3 per pile)Mobilisation: 1 day (Allow for 2 days)Next trade - Excavate and blind around piles (for ring beam) - start 7 elasped days after last piles in the run are complete (4 working and 7 elasped days after piling start based on Hit 1 miss 3 method and 12No/d). 34 linear metres released for Groundworker to start.All piles 600mm in dia. No smaller piles or grout tubes used as described in the post by technical development. The face of the basement wall will be faced with a single skin of blockwork at a later date (non critical).Method: Hit 1, Miss 32 rate statements found; left for an editor | — | Contigous Piling |
| Copper RoofingMetal Roof Decking | Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Copper Roofing Flat Roof Copper Work = 3.0 m2/day Sloping Roof Copper Work = 2.7 m2/day2 rate statements found; left for an editor | — | Copper Roofing |
| Covered Steel FootbridgeBridges | Simple universal beam steel bridge in modular sections, welded on site. 16 truss sections each 15 m in length, supported on H-frame vertical columns / supports.Support Steelwork Fabrication (4 bays) = 25 daysSupport Steelwork Erection (4 bays) = 30 daysTruss erections (4 bays) = 18 daysPaintwork To Steel (16 bays) = 35 daysBridge Deck Concrete Works (16 bays) = 60 days (staggered)Bridge Lighting, Roof etc (16 bays) = 40 daysBridge Finishing, Handrails and Grano = 14 daysStructural Steelwork...Task / DescriptionSlow Ave Fast Units Simple Universal Beam Steel Bridge, erect support steel H frames- 1.2 - days/no Simple Universal Beam Steel Bridge, erect 15m truss- 3.3 - m/day | — | Covered Steel Footbridge |
| Crane Grab Hoists & Cranes | Tender rates are often quoted as between 20 and 25 m3/hr. With adequate supervision and sufficient loose spoil material supplied to the crane drop area, these rates can easily be increased. Grabs mounted on crawler cranes, rates depend on... Depth of the spoil to be removed Operative supervision - breaks etc Management and availibility of lorries Efficiency and utlisation of banksmen Transport of spoil to crane drop area Down time of machinery and staff Clamshell Grab Mounted on a crawler crane... 2.0 m3 bucket (HK Cut & Cover Tunnels) 33 m3/hr 1.5 m3 per lift 2.9 mins per lift 2.5 m3 bucket (HK Station Box) 41 m3/hr 2.0 m3 per lift 3.1 mins per lift3 rate statements found; left for an editor | — | Crane Grab |
| Curtain WallingFacade Waterproofing | Typical Curtain Walling = 25.0 m2/day | 25 m2 per dayper dayParsed | Curtain Walling |
| Curtain WallingBuilding Frameworks | Curtain Walling rateAssume 30m2 per week for general curtain wallingTask / DescriptionSlow Ave Fast Units Vertical Glazed Lights, 6m x 2.5m- 14.5 - m2/day Vertical Glazed Walls, large scale- 70.0 - m2/day Clerestory Frame/Glazing, 3m x 4m- 28.0 - m2/day Oriel Window Frame/Glazing, 4m x 2m- 35.0 - m2/day Glazed Curtain Wall, First Fix- 1.2 - m2/hr Glazed Curtain Wall, Second Fix- 1.1 - m2/hr High Quality Glazed Curtain Walling- 25.0 - m2/day | 30 m2 per weekper weekParsed | Curtain Walling |
| Cut and Cover TunnelsTunnelling & Mining | — | Cut and Cover Tunnels |
1–50 of 202
These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.