How to link Access to P3?

Vincent HauMember for 24 years 7 months
Created
5
3
0
As i read the messages which post by Ali Hamouda on 11.02.2002 band i still do not understand how to link my access data base to P3? because my Q.S using the M.Access to prepare the tender and directly the Resourses and production rates are already inside the files.

I want to transfer the resourse and production rates(mean UPT) to P3.

1)Can anyone tell me how to establish the link at OCBC step by step or where i can get these info?

2) How to link the access data base to P3?

5 replies

Oldest first
  1. 0
    Khalid Abdelaal ·
    Try This Site
    Link
  2. 0
    Roger Gibson ·
    There is an add-on made by Primaplan called Flint that allows you to do
    this, have a look at Primaplan.com
  3. 0
    M Colon ·
    On the P3 knowledgebase

    Bulletin Number: 200011616333

    You need to install the Pervasive 32-bit ODBC driver that Primavera sends out, i.e. "Pervasive Software ODBC-32" version 2.04.02.10.

    1. See Technical Bulletin 200052692630 - "Setting up SureTrak v3.0 for 32bit ODBC", and Technical Bulletin 1999330113639, "How to install the Pervasive 32-bit ODBC drivers" for instructions on installation and configuration.

    2. If using SureTrak, save your project as a Project Groups type project if you haven’t done this already.

    3. Go to Tools, Update Data Dictionary to create your *DDF files .

    4. Create the Data Sources for the SureTrak projects you want to work with through the 32-bit ODBC driver in Control Panel.

    5. Make sure that the project is not open in SureTrak or P3.

    6. In Microsoft Access go to File, New Database to create a new database.

    7. Give the database a name.

    I hope this helps
  4. 0
    Vincent Hau ·
    Thank You.is a very useful info. and i am trying now.
  5. 0
    Vincent Hau ·
    Thank You for your valuable info.