Primavera Project Planner

Ali VessaliMember for 25 years 1 month
Created
2
1
0
Cost Loading in P3:

Lets talk more about this topic and share expriences.

2 replies

Oldest first
  1. 0
    Khalid Abdelaal ·
    Dear Ali check the following link and reply

    Presentation
    make sure that you have acrobat reader

    Khalid Abdelaal
  2. 0
    Ali Vessali ·
    Dear Khalid Abdelaal,

    Thank you for your reply. That link was very useful. More or less I used the method in my projects before.
    In my last cost loading schedule for a construction project in South Carolina, I have used earned value analisys in P3. The Sub-Contractores were introduced as Resources and Project Billing Codes were introduced as Cost Accounts in P3. For each activity in the schedule I assigned the proper Sub-Contractors and Billing Codes by using of Resource Assignment method in P3.
    Now Im able to create the Project Cash Flow Diagram (or S-Curve) and all monthly invoices prepare directly from P3.
    Again thank you for your reply and keep in touch.
    Ali