Project % Completion - 1 decimal place possible?

P3 SchedulerMember for 24 years 9 months
Created
4
31
0
The % Complete column always shows percentage with rounded figure (i.e. without decimal).
Is it possible to show the percentage with 1 decimal place, eg. 30.4% instead of 30% ?

I noticed that if I schedule the project from the menu Tools->Schedule..., the report
on the screen will show the percent complete in 1 decimal figure.

Thanks and best regards,
CS Ong

4 replies

Oldest first
  1. 0
    Admin Team ·
    Hi there CS,

    I know that you can specify either 0 or 2 decimal places for cost and resource data via the "Project > Overview > Decimal" menu options but as far as we are aware, you can’t change how the PC field is displayed within P3.

    Can you not change the display within one of the reports?

    Does that help?

    Regards.
  2. 0
    Ali Vessali ·

    Project % Completion - 1 decimal place possibl

    Hi there,
    You can use Report Writer to show all numeric field such as percentage complete (PCT) with 2 decimal places.

    Thanks,
    Ali
  3. 0
    Zq qz ·
    Hello,
    You can add custom data item then do some global change to update custom data item you add.
    Regards,
  4. 0
    Mk Tse ·
    P3 Scheduler,
    May I know why 1 decimal place. If look consistant to all reports, the above posted got hints already. I wonder any special requirement.