Activity Codes in Primavera

Nishath AhsanMember for 23 years 6 months
Created
8
1
0
Hi Every one!

Can any one tell me if there are any standardized activity codes available for primavera to be useed in construction projects. In awhite paper on primavera i have read that such a code has been made by CSI - Construction Standards Institute but i am unable to source it.

Thanks in anticipation

Regards

Nishath

8 replies

Oldest first
  1. 0
    Tara Muddappa ·
    Hi Nishanth,

    We had used the attached norm for our project, using CSI code as the guideline.
    Hope this is of some use to you !

    Regards,

    Tara Muddappa

    A. Work Breakdown Structure

    Headquarters Building Project

    1. Level 1 : Project

    A : Headquarters Building

    2. Level 2 : Object (Area/Building,Bill No.)

    A : Milestones
    B : Mobilization
    C : Tower Building A and B
    D : Car Park Building
    E : External Works
    F : Provisional Sum

    3. Level 3 : Division
    :01 General
    :02 Site Works
    :03 Concrete Works
    :04 Masonary
    :05 Metals
    :06 Wood and Plastic
    :07 Thermal and Moisture Protection
    :08 Doors and Windows
    :09 Finishes

    :10 Specialities
    :11 Equipment
    :12 Furnishings
    :13 NSC,Curtainwall
    :14 Traction and Hydraulic Lifts
    :15 Mechanical Works
    :16 Electrical Works
    :17 External Paving and Landscaping

    4. Level 4 : Trade

    :01 General Milestones
    :02 Tower Milestones
    :03 Carp Milestones
    :04 External Works Milestones
    :05 Mobilization
    :06 Construction Equipment
    :07 Preliminaries
    :08 Final Cleaning
    :09 Demobilization

    :10 Excavation Perimeter Retention System
    :11 Excavation and Backfill
    :12 Anti-thermite treatment and Others
    :13 Concrete Works
    :14 Embedded Structure Steel
    :15 Structural Steel Works, Atrium Facade
    :16 Structural Steel Works,Stair C
    :17 Structural Steel Works , Fin Brackets
    :18 Structural Steel Works,Roof and Atrium Skylight
    :19 Structural Steel Works,Others

    :20 Floor Screed
    :21 Accessories to Bed
    :22 Unit Masonry Assemblies
    :23 External Stone Cladding
    :24 Waterproofing and Roofing
    :25 Handrails and Balustrades
    :26 Metal Fabrications
    :27 Ornamental Metals
    :28 Fire Protection
    :29 Proprietary Roof System

    :30 Curtainwall Type A, @ Wing A(NSC)
    :31 Curtainwall Type A, @ Wing B(NSC)
    :32 Curtainwall Type B, Atrium(NSC)
    :33 Curtainwall Type C, C1, H, H1(NSC)
    :34 Curatinwall Type A1(NSC)
    :35 Curtainwall Type G, G1(NSC)
    :36 Curtainwall Type D,Wing A(NSC)
    :37 Curtainwall Type D,Wing B(NSC)
    :38 Skylight and Type F(NSC)
    :39 Curtainwall Type E,E1,E2,Canopy(NSC)

    :40 Gypsum Board System
    :41 Gypsum Plastering
    :42 Plasterboard Ceiling and Bulkhead
    :43 Accoustic Tile Ceiling
    :44 Linear Metal Ceiling
    :45 Metal Tile Ceiling
    :46 Metal Mesh Ceiling
    :47 Ceramic Tiles
    :48 Interior Stone Flooring
    :49 Steel Doors and Shutters

    :50 Wood Doors
    :51 Aluminium and Glass Doors
    :52 Screens and Acid Etched Panels
    :53 Louvers and Vents
    :54 Wood Skirting
    :55 Carpentry Panelling
    :56 Joinery Fittings
    :57 Timber Flooring
    :58 Resilient Flooring
    :59 Carpet Tiles

    :60 Accessories to Floor Finishes
    :61 Painting
    :62 Spray on Fire Protection
    :63 Access Flooring
    :64 Partition System
    :65 Doors and Glazed Units in Partition
    :66 Toilet Partition
    :67 Taoilet Accessories and Sanitary Ware
    :68 Door Hardware
    :69 Specialities and Others

    :70 Parking Control and Loading Dock Equipment
    :71 Health Club Equipment
    :72 Sheet Metal Flashing and Trim
    :73 Blind and Curtain System
    :74 Entrance Matting, Others
    :75 Hydraulic Lift
    :76 Goods and Passenger Lift
    :77 Not Used
    :78 Not Used
    :79 Not Used

    :80 Passengers Lifts-Low Rise
    :81 Passenger Lifts-High Rise
    :82 Goods Lift
    :83 Not Used
    :84 Doors(NSC)
    :85 Building Maintenance Equipment(NSC)
    :86 Carpark,Curtainwall(NSC)

    A0 Piping Works For Fire Protection
    A1 Valves and Ancilliaries for Fire Protection
    A2 Equipment For Fire Protection
    A3 Fire Supression System
    A4 T and C for Fire Protection
    A5 Piping Works For Rainwater
    A6 Equipment For Rainwater
    A7 Insulation for Rainwater
    A8 T and C For Rainwater
    A9 Piping Works For Soil and Waste

    B0 Condensate Piping For Soil and Waste
    B1 Ancilliaries For Soil and Waste
    B2 Equipment For Soil and Waste
    B3 T and C For Soil and Waste
    B4 Piping Works For Dom Cold Water
    B5 Insulation For Dom Cold Water
    B6 Valves and Ancillaries For Dom Cold Water
    B7 Equipment For Dom Cold Water
    B8 Sanitaryware Fittings
    B9 T and C Dom Cold Water

    C0 Piping Works For Dom Hot Water
    C1 Valves and Ancillaries For Dom Hot Water
    C2 Equipment For Dom Hot Water
    C3 Insulation For Dom Hot Water
    C4 T and C for Dom Hot Water
    C5 Chilled Water Piping
    C6 Valves and Ancilliaries For CHW
    C7 Equipment For CHW
    C8 Insulation and Protective Covers for CHW
    C9 T and C For CHW

    D0 Ductworks
    D1 Thermal Duct Insulation
    D2 Dampers,Grilles and Diffusers
    D3 Equipment For Air System
    D4 T and C For Air System
    D5 Hardware For BMS
    D6 Motor Control Panels
    D7 DGP
    D8 BMS Wiring
    D9 Sensors,Control Valves and Motorised Dampers

    E0 T and C For BMS
    E1 Fuel Oil Piping Works
    E2 Equipment For FOP
    E3 T and C For FOP
    E4 Piping Works For Swimming Pool
    E5 Equipment For Swimming Pool
    E6 T and C Swimming Pool

    F0 Main Distribution-MV Installation
    F1 Main Circuits( cabling and Piping)
    F2 Electrical Power Generation
    F3 Submain Distribution Equipments
    F4 Submain Distribution (cabling and Piping)
    F5 Vertical BusbarTrunking
    F6 Distribution Boards
    F7 Uninteruptable Power Supply Units
    F8 General Power Installation(Cabling and Piping)
    F9 General Power Installation(Devices and Accessories)

    G0 Equipment Points(Cabling and Piping)
    G1 Equipment Points(Devices and Accessories)
    G2 Voice and data(Raceways and Containment)
    G3 Gen. Emergency Lighting(Cabling and Piping)
    G4 Gen. Emergency Lighting(Equipment,light Control)
    G5 FA,PA and VA (Cabling and Piping).
    G6 FA,PA and VA (Equipment and Devices).
    G7 Testing and Commissioning(Electrical)
    G8 Electric Sundries

    H0 Equipment(Provisions)
    H1 Cabling(Provisions)
    H2 Security Cabling To Equipment(Provisions)
    H3 Specialist Lighting(Provisions)
    H4 Kitchen Equipment(Provisions)
    H5 Landscaping and Water Features(Provisions)
    H6 Stone Work(Provisions)
    H7 Timber Veneer(Provisions)
    H8 FF and E(Provisions)
    H9 Signage(Provisions)

    B. Activity ID

    Digit 1 :Object
    2and3:Division
    4and5:Trade
    6 : Category
    7,8and9: Unique number




    Category
    :01 Bid and Award Contracts
    : 02 Pre-Construction Activities
    : 03 to 09 On-Site Construction

  2. 0
    Forum Guest ·
    Thanks Tara for your reply.

    I see that u r from UAE. I am currently working in Dubai. If you are free we can exchange notes on the phone. Can i have your contact number???
    REgards

    Nishath
  3. 0
    Nishath Ahsan ·
    Hi this is nishath again,

    The codes you have provided is very helpful. Right now i am working in the Infrastructure field. Do you have similar codes for infrastructure field. Also where can i find the original codes that have been made by CSI.

    thanks again

    Nishath
  4. 0
    Forum Guest ·
    Hi Team!

    Do any of your good people feel like formalising these P3 codes into something that we could put on the site as a possible suggested / uniform means of coding various types of programme?

    We obviosuly respect the CSI system etc, if we were to utilize, some or all of their coding structure we could always approach CSI to see if we can post/recommend your suggested programme coding method etc ??

    What do you think. Is there any scope here for us all?

    Regards.
    For Planning Planet Team.

    Keep up the great work.
  5. 0
    Forum Guest ·

    Activity Codes in Primavera

    Standard lists of codes are available for many projects but are sometimes hard to obtain and often are only a guide as every project has its own individual requirements.

    As a project planner I see one of my tasks is to develop a list of Activity codes that allows me to schedule and report a project in both the planning and execution of a project that is accepted and understood by the project team.

    A project planner is a person who should be able to look as a project and the tool that is being used to schedule the project and advise the project team on how to best code the project.

    I often consider Primavera Code Dictionaries under the following headings:

    Phase: e.g. Design, Procure, Install, Test and Litigate!

    Stage: This would break down the project following the PRINCE2 philosophy,

    Discipline: This would include legal, consultation, civil, mechanical, electrical, etc

    Trade: similar to Discipline but used by the building industry, carpenters, brickies, plumbers etc

    Process: Approvals, Guidelines, Land Acquisition, Mediation, Planning, Quality Assurance, Project Management, Estimating.

    Area: dividing the project into physical areas by level or geographical areas.

    Product Break Down: breaking the project down into its physical deliverables following the PRINCE2 methodology.

    System Breakdown: breaking the project down into the respective systems and subsystems (System Engineering)

    Organizational Breakdown Structure, breaking down the project by organization responsible for the project.

    Assignment: Who is doing the work.

    Responsibility: Who is supervising the work

    Contract Breakdown Structure, using the contract schedule to dissect a project.

    Work Breakdown Structure, a structure a client wants the project reported by, for want of a better description.

    Cost Account, a breakdown of how the cost are to be collected.

    There are probably a few more acronyms which may be listed but the important thing is that the planner understands the project and may be able to advise the players (stakeholders) of the options in coding a project and advise on the best method of breaking down the project.

    Regards
    Paul E Harris
    www.eh.com.au
  6. 0
    Katalin Hovanyi ·
    Haliho,
    http://fire.nist.gov/bfrlpubs/build99/PDF/b99080.pdf
    You can find in this publication a very nice Level 4 structure for building construction (109 pages in PDF format!). I use this for my new building projects, because with a very few changes I can apply quickly.

    There are a few good links here
    http://www.constructioneducation.com/UNIFORMAT.htm
    Good Luck

  7. 0
    Kim King ·

    Thanks all, is there a

    Thanks all, is there a standard list of activity codes for turnaround projects?

  8. 0
    Zoltan Palffy ·

    here is a simple

    here is a simple one 

    Phase

    Building

    Level 

    Area

    Responsibility 

    Feature of work