Hi Planner,

Joined this group recently. Intersting to find various topics ......now my prob not really a planning issue, if any one can help......
In windows XP, with the feature of running the incompatible software in Win98/Me mode I am able to use the P3 ver 2 software. However the resourse profile display blinks continuosly and the printer wont accept more than a page at a time. While trying to print two or more pages a general error appears. Other softwares I am not facing any problem.

Thanks

3 replies

Oldest first
  1. 0
    Ronald Winter ·
    There is your problem. You are running an out-of-date P3 on a new computer. I just looked at the P3 technical support site and the knowledgebase does not even include problem fixes for Version 2.

    The Current version of P3 is Version 3.1, Service Pack 1. The Knowledgebase states that you must be running Btreve Version 6.15 of later to run XP. If your version of P3 is working at all, then count your blessings.
  2. 0
    Nihat Yildirim ·
    P3 2.0 is not supported anymore and wont work properly on Win XP.
    You have to switch to the current version, 3.1
  3. 0
    Jorge Taguinod ·
    You need to be under maintenance though, to make the switch for free.

    P3 3.1 has great new features which makes the investment worthwhile.

    - It has editable period performance. The period performance eliminates the "inconsistent s-curve" previously plaguing earlier versions of P3.

    - Progress spotlighting eliminates the need to perform a filter to update activities due this period.

    - A progress line can now be displayed to show which activities are delayed or advanced at a glance.

    - Project codes allow easy input of codes that are common across subprojects.

    - resource assignment allow you to load similar resources with similar UPT or BQ across multiple activities in one shot

    - Most of all, you now have the Primavera Post Office!

    - plus other nifty items!

    Happy planning!

    Jorge