Can anyone help please !!!
I have a project group in P3 my satelite offices only have suretrack, they can open the files but one of the columns I have used by adding into the custom data items box does not appear as a column or as an option for a column in suretrack. Is suretrack restricted to its default column titles and additional activity codes only, and not able to recognise custom data. If anyone knows away around this I would be very grateful

Cheers

1 reply

Oldest first
  1. 0
    Jorge Taguinod ·
    Hi Martin!

    Sorry but some data fields in P3 cannot be read by SureTrak. These include custom data items, cost accounts, period performance, chaning unit prices of resources, etc.

    Best regards,

    Jorge