P3 resource-activity pct relationships

Forum GuestMember for 17 years 8 months
Created
2
2
0
Hi friends,
I have a problem,
I have an activity that 3 resources connect to activity,
Problem : When I change Actual to date of these resources, activitys PCT does not change. Activitys PCT change only on activity form screen (PCT or RD) I want that : When I change tese resources ATD or ATP, activitys PCT change by resources unit price x resources actual guantity

Thank you for your ideas and helps.
E-mail : halit.hunkar@alsim.alarko.com.tr

Berke Hunkar

2 replies

Oldest first
  1. 0
    Forum Guest ·
    Hi,

    Activity PCT field in Activity Form is a user input field (where u specify how much is activitys schedule percent complete), and not a calculated field.

    Again, resource rate x resource actual quantity = resource actual cost (and not PCT)

    However, this multiplication takes place and you get actual cost of resource as actual to date in cost field of activity..

    As per this actual cost, you will also get percent complte & percent expended as well in same window, taken from activity form.

    regards
    sonia
  2. 0
    Jorge Taguinod ·
    Hi Berke,

    P3 does not work this way.

    ATD & ATP are computed from Activity PCT. Not vice versa.

    Best regards,

    Jorge