LEVELLING OF RESOURCE

Bhuvaneswaran VelayudhemMember for 23 years 4 months
Created
4
1
0
Any expert can you explain me how to convert the level dates (AFTER LEVELLING THE RESOURCE) into constrained date in P3? or Is it possible to fix the levelled dates even after scheduling (F9) in P3?

4 replies

Oldest first
  1. 0
    Steven Oliver ·
    Try creating a custom data item to hold the levelled value of early start, and after re-scheduling set the early start constraint equal to the custom data item
  2. 0
    Martin Polack ·
    ...or maybe you may make a copy of the "resource levelled" scheduled and use it as a Target 1 (or 2). Then you can prepare a layout comparing that Target against your current schedule.
  3. 0
    Bhuvaneswaran Velayudhem ·
    THXS A LOT.
  4. 0
    Jorge Taguinod ·
    You can run a Global Change to automatically constrain the leveled early start dates:

    Create a new Global Change statement and in the Then area, write:

    SNE EQ ES

    This should work.

    regards,

    Jorge Taguinod

Log in or join to reply